Details for: PGE AL 5121-E.pdf


Click on the image for full size preview

Document data

Erik Jacobson
Director
Regulatory Relations

Pacific Gas and Electric Company
77 Beale St., Mail Code B13U
P.O. Box 770000
San Francisco, CA 94177
Fax: 415-973-3582

August 8, 2017

Advice 5121-E
(Pacific Gas and Electric Company ID U39 E)

Public Utilities Commission of the State of California
Subject:

Submits Notice of Construction, Pursuant to General Order
131-D, for the Construction of Maple Creek-Willow Creek 60 kV
Reliability Project in the County of Humboldt

Pacific Gas and Electric Company (“PG&E” or “the Company”) hereby submits
notice pursuant to General Order (G.O.) 131-D, Section XI, Subsection B.4, of
the construction of facilities that are exempt from a Permit to Construct.
Purpose
This advice letter provides a copy of the Notice of Proposed Construction
(Attachment I) and the Notice Distribution List, which comply with the noticing
requirements found in G.O. 131-D, Section XI.
Background
To improve electric service reliability to customers in rural Humboldt County,
PG&E is proposing to replace poles and associated hardware on the
approximately 20-mile-long Maple Creek-Willow Creek 60 Kilovolt (kV) Power
Line in Humboldt County (existing easement and franchise). The project begins
at Maple Creek Substation, located approximately 0.1 mile west of the
intersection of Maple Creek Road and Powerline Road in Maple Creek. The line
continues roughly northeast through undeveloped Humboldt County and Six
Rivers National Forest to Willow Creek Substation, located approximately 0.4
mile northwest of the intersection of Highway 96 and Brannan Mountain Road in
Willow Creek. The northeastern half of the project generally follows Highway
299. PG&E will replace 127 wood structures with new wood and light-duty steel
poles and will combine several two- and three-pole structures into single-pole
structures. The replacement poles will be approximately 5 feet shorter to 34 feet
taller than the existing poles to ensure compliance with CPUC General Order 95
minimum ground-to-conductor clearance requirements. PG&E will also replace
the guys/anchors that support the new line as needed. Finally, approximately 6





- Page 1 -

Advice No. 5121-E -2- August 8, 2017 miles northeast of the Maple Creek Substation, PG&E will replace one approximately 50-foot-tall wood pole and manual switch with a new approximately 50-foot-tall tubular steel pole equipped with automated switch equipment. The project will avoid impacts to watercourses and other nearby resources. Helicopters will be used to facilitate construction in some areas. Construction is tentatively scheduled to begin in summer 2018 or as soon as practicable after project approval. Construction is scheduled to be complete in fall 2018 or as soon as possible after construction begins. CPUC General Order 131-D, Section III, Subsection B.1, exempts projects meeting specific conditions from the CPUC’s requirement to file an application requesting authority to construct. The Company believes this project qualifies for the following exemption(s), g. “power line facilities or substations to be located in an existing franchise, road-widening setback easement, or public utility easement; or in a utility corridor designated, precisely mapped and officially adopted pursuant to law by federal, state, or local agencies for which a final Negative Declaration or EIR [Environmental Impact Report] finds no significant unavoidable environmental impacts.” This filing will not cause the withdrawal of service, or conflict with any other rate schedule or rule. Protests Anyone wishing to protest this filing may do so by filing a protest with the CPUC and the Company by August 28, 2017, which is 20 days after the date of this filing. Protests should be mailed to the following address: CPUC Energy Division ED Tariff Unit 505 Van Ness Avenue San Francisco, California 94102 Facsimile: (415) 703-2200 E-Mail: EDTariffUnit@cpuc.ca.gov Copies of protests also should be mailed to the attention of the Director, Energy Division, Room 4004, at the address show above. The protest also should be sent via U.S. mail (and by facsimile and electronically, if possible) to PG&E at the address shown below on the same date it is mailed or delivered to the Commission:
- Page 2 -

Advice No. 5121-E -3- August 8, 2017 David T. Kraska Attorney, Law Department Pacific Gas and Electric Company P.O. Box 7442 San Francisco, California 94120 Facsimile: (415) 973-0516 Erik Jacobson Director, Regulatory Relations c/o Megan Lawson Pacific Gas and Electric Company P.O. Box 770000, Mail Code B13U San Francisco, California 94177 Facsimile: (415) 973-3582 E-Mail: PGETariffs@pge.com Persons or groups may protest the proposed construction if they believe that the Company has incorrectly applied for an exemption or that the conditions set out in Section III.B.2 of G.O. 131-D exist. Public Comment Individuals or groups who do not file an official protest may still submit a comment on the request to the Energy Division at the address noted above, referencing Advice Letter 5121-E. Effective Date The Company requests that this Tier 2 advice filing become effective on September 7, 2017, which is 30 days after the date of filing. (In accordance with G.O. 131-D, construction will not begin until 45 days after notice is first published.) Notice A copy of this advice letter is being sent electronically and via U.S. Mail to parties shown on the attached list, including the parties listed in G.O. 131-D, Section XI, Paragraphs B.1 and B.2. These parties are identified in the “Notice Distribution List” included in Attachment I. All electronic approvals should be sent to e-mail PGETariffs@pge.com. Advice letter filings can also be accessed electronically at http://www.pge.com/tariffs/.
- Page 3 -

Advice No. 5121-E -4- /S/ Erik Jacobson Director, Regulatory Relations cc: Parties Listed in G.O. 131-D, Paragraphs B.1 and B.2 Attachments August 8, 2017
- Page 4 -

CALIFORNIA PUBLIC UTILITIES COMMISSION ADVICE LETTER FILING SUMMARY ENERGY UTILITY MUST BE COMPLETED BY UTILITY (Attach additional pages as needed) Company name/CPUC Utility No. Pacific Gas and Electric Company (ID U39 E) Utility type: Contact Person: Kingsley Cheng  ELC  GAS  PLC  HEAT Phone #: (415) 973-5265  WATER E-mail: k2c0@pge.com and PGETariffs@pge.com EXPLANATION OF UTILITY TYPE ELC = Electric PLC = Pipeline GAS = Gas HEAT = Heat (Date Filed/ Received Stamp by CPUC) WATER = Water Advice Letter (AL) #: 5121-E Tier: 2 Subject of AL: Submits Notice of Construction, Pursuant to General Order 131-D, for the Construction of Maple Creek-Willow Creek 60 kV Reliability Project in the County of Humboldt Keywords (choose from CPUC listing): Compliance, Power Lines AL filing type:  Monthly  Quarterly  Annual  One-Time  Other _____________________________ If AL filed in compliance with a Commission order, indicate relevant Decision/Resolution #: N/A Does AL replace a withdrawn or rejected AL? If so, identify the prior AL: No Summarize differences between the AL and the prior withdrawn or rejected AL: ____________________ Is AL requesting confidential treatment? If so, what information is the utility seeking confidential treatment for: No Confidential information will be made available to those who have executed a nondisclosure agreement: N/A Name(s) and contact information of the person(s) who will provide the nondisclosure agreement and access to the confidential information: __________________________________________________________________________________________________ Resolution Required? Yes No Requested effective date: September 7, 2017 N No. of tariff sheets: N/A Estimated system annual revenue effect (%): N/A Estimated system average rate effect (%): N/A When rates are affected by AL, include attachment in AL showing average rate effects on customer classes (residential, small commercial, large C/I, agricultural, lighting). Tariff schedules affected: N/A Service affected and changes proposed: N/A Pending advice letters that revise the same tariff sheets: N/A Protests, dispositions, and all other correspondence regarding this AL are due no later than 20 days after the date of this filing, unless otherwise authorized by the Commission, and shall be sent to: California Public Utilities Commission Director, Energy Division 505 Van Ness Ave., 4th Floor San Francisco, CA 94102 E-mail: EDTariffUnit@cpuc.ca.gov Pacific Gas and Electric Company Attn: Erik Jacobson, Director, Regulatory Relations c/o Megan Lawson 77 Beale Street, Mail Code B13U P.O. Box 770000 San Francisco, CA 94177 E-mail: PGETariffs@pge.com
- Page 5 -

Attachment I NOTICE OF PROPOSED CONSTRUCTION Para más detalles llame 1-800-660-6789 PROJECT NAME: Maple Creek – Willow Creek 60 kV Power Line Reliability Project - (Humboldt County, T.0000609) ADVICE LETTER NUMBER: 5121-E Proposed Project: To improve electric service reliability to customers in rural Humboldt County, Pacific Gas and Electric Company (PG&E) is proposing to replace poles and associated hardware on the approximately 20-mile-long Maple Creek – Willow Creek 60 Kilovolt (kV) Power Line in Humboldt County (existing easement and franchise). The project begins at Maple Creek Substation, located approximately 0.1 mile west of the intersection of Maple Creek Road and Powerline Road in Maple Creek. The line continues roughly northeast through undeveloped Humboldt County and Six Rivers National Forest to Willow Creek Substation, located approximately 0.4 mile northwest of the intersection of Highway 96 and Brannan Mountain Road in Willow Creek. The northeastern half of the project generally follows Highway 299. PG&E will replace 127 wood structures with new wood and light-duty steel poles and will combine several two- and three-pole structures into single-pole structures. The replacement poles will be approximately 5 feet shorter to 34 feet taller than the existing poles to ensure compliance with CPUC General Order 95 minimum ground-to-conductor clearance requirements. PG&E will also replace the guys/anchors that support the new line as needed. Finally, approximately 6 miles northeast of the Maple Creek Substation, PG&E will replace one approximately 50-foot-tall wood pole and manual switch with a new approximately 50foot-tall tubular steel pole equipped with automated switch equipment. The project will avoid impacts to watercourses and other nearby resources. Helicopters will be used to facilitate construction in some areas. Construction is tentatively scheduled to begin in summer 2018 or as soon as practicable after project approval. Construction is scheduled to be complete in fall 2018 or as soon as possible after construction begins. Exemption from CPUC Permit Requirement: CPUC General Order 131-D, Section III, Subsection B.1, exempts a utility from the CPUC’s requirement to file an application requesting authority to construct if a project meets specific conditions. This project qualifies for the following exemption(s): g. “power line facilities or substations to be located in an existing franchise, road-widening setback easement, or public utility easement; or in a utility corridor designated, precisely mapped and officially adopted pursuant to law by federal, state, or local agencies for which a final Negative Declaration or EIR [Environmental Impact Report] finds no significant unavoidable environmental impacts.” Additional Project Information: To obtain further information on the proposed project, please call PG&E’s Project Information Line at (415) 973-5530. Public Review Process: Individuals or groups may protest the proposed construction if they believe that PG&E has incorrectly applied for an exemption or that the conditions set out in Section III.B.2 of General Order 131-D exist; a. b. c. There is reasonable possibility that the activity may have an impact on an environmental resource of hazardous or critical concern where designated, precisely mapped and officially adopted pursuant to law by federal, state, or local agencies; or The cumulative impact of successive projects of the same type in the same place, over time, is significant; or There is a reasonable possibility that the activity will have a significant effect on the environment due to unusual circumstances. Protests should include the following: 1. 2. 3. 4. Your name, mailing address and daytime telephone number. Reference to the CPUC Advice Letter Number and Project Name. A clear description of the reason for the protest. Whether you believe that evidentiary hearings are necessary to resolve factual disputes. Protests for this project must be filed by August 28, 2017 at the following address: Director, Energy Division ED Tariff Unit California Public Utilities Commission 505 Van Ness Avenue, Fourth Floor San Francisco, California 94102 With a copy mailed to: David Kraska, Law Department Pacific Gas and Electric Company P.O. Box 7442 San Francisco, California 94120 PG&E must respond within five business days of receipt and serve its response on each protestant and the Energy Division. Within 30 days after PG&E has submitted its response, the CPUC Executive Director will send you a copy of an Executive Resolution granting or denying PG&E’s request and stating the reasons for the decision. Assistance in Filing a Protest: If you need assistance in filing a protest, contact the CPUC Public Advisor: email: public.advisor@cpuc.ca.gov or call: 1-866-849-8390 (toll-free), or (415) 703-2074, or TTY (415) 703-5258. (T.00000193/SAP Order No. 74000976 /MWC 93C)
- Page 6 -

Public Comment: Even if you do not want to file an official protest, you may still comment on the request. To do so, send your comments to the Energy Division at the address noted above. Please reference Advice Letter 5121-E.
- Page 7 -

Notice Distribution List Maple Creek-Willow Creek 60 kV Power Line Reliability Project (Humboldt County) Advice 5121-E Energy Commission Mr. Robert Oglesby, Executive Director California Energy Commission 1516 Ninth Street, Mail Stop 39 Sacramento, California 95814 Rob.Oglesby@energy.ca.gov Mr. Drew Bohan, Deputy Director California Energy Commission 1516 Ninth Street, Mail Stop 39 Sacramento, California 95814 Drew.Bohan@energy.ca.gov California Department of Fish and Wildlife Mr. Patrick Moeszinger California Department of Fish and Wildlife, North Central Region 1701 Nimbus Road Rancho Cordova, CA 95670 Patrick.Moeszinger@wildlife.ca.gov Six Rivers National Forest Mr. Michael Green Acting Forest Supervisor Six Rivers National Forest 1330 Bayshore Way Eureka, CA 95501 County of Humboldt Mr. John H. Ford, Director Humboldt County Planning and Building Department 3015 H St. Eureka, CA 95501 jford@co.humboldt.ca.us Newspaper Eureka Times-Standard
- Page 8 -

PG&E Gas and Electric Advice Filing List AT&T Division of Ratepayer Advocates Albion Power Company Alcantar & Kahl LLP Anderson & Poole Atlas ReFuel BART Don Pickett & Associates, Inc. Douglass & Liddell Downey & Brand Ellison Schneider & Harris LLP Evaluation + Strategy for Social Innovation G. A. Krause & Assoc. GenOn Energy Inc. GenOn Energy, Inc. Goodin, MacBride, Squeri, Schlotz & Ritchie Green Charge Networks Green Power Institute Hanna & Morton ICF International Power Technology Intestate Gas Services, Inc. Barkovich & Yap, Inc. Bartle Wells Associates Braun Blaising McLaughlin & Smith, P.C. Braun Blaising McLaughlin, P.C. CENERGY POWER CPUC CalCom Solar California Cotton Ginners & Growers Assn California Energy Commission California Public Utilities Commission California State Association of Counties Calpine Casner, Steve Center for Biological Diversity City of Palo Alto City of San Jose Clean Power Clean Power Research Coast Economic Consulting Commercial Energy Cool Earth Solar, Inc. County of Tehama - Department of Public Works Crossborder Energy Crown Road Energy, LLC Davis Wright Tremaine LLP Day Carter Murphy Defense Energy Support Center Dept of General Services Kelly Group Ken Bohn Consulting Leviton Manufacturing Co., Inc. Linde Los Angeles County Integrated Waste Management Task Force Los Angeles Dept of Water & Power MRW & Associates Manatt Phelps Phillips Marin Energy Authority McKenna Long & Aldridge LLP McKenzie & Associates Modesto Irrigation District Morgan Stanley NLine Energy, Inc. NRG Solar Nexant, Inc. ORA Office of Ratepayer Advocates Office of Ratepayer Advocates, Electricity Planning and Policy B OnGrid Solar Pacific Gas and Electric Company Praxair Regulatory & Cogeneration Service, Inc. SCD Energy Solutions SCE SDG&E and SoCalGas SPURR San Francisco Water Power and Sewer Seattle City Light Sempra Energy (Socal Gas) Sempra Utilities SoCalGas Southern California Edison Company Southern California Gas Company (SoCalGas) Spark Energy Sun Light & Power Sunshine Design Tecogen, Inc. TerraVerde Renewable Partners TerraVerde Renewable Partners, LLC Tiger Natural Gas, Inc. TransCanada Troutman Sanders LLP Utility Cost Management Utility Power Solutions Utility Specialists Verizon Water and Energy Consulting Wellhead Electric Company Western Manufactured Housing Communities Association (WMA) YEP Energy Yelp Energy
- Page 9 -