Erik Jacobson
Director
Regulatory Relations
Pacific Gas and Electric Company
77 Beale St., Mail Code B13U
P.O. Box 770000
San Francisco, CA 94177
Fax: 415-973-3582
December 26, 2018
Advice 5455-E
(Pacific Gas and Electric Company ID U39 E)
Public Utilities Commission of the State of California
Subject:
Submits Notice of Construction, Pursuant to General Order 131-D,
for the Construction of Cordelia #2 60kV Power Line Tap Switch
Replacement Project, in the City of Fairfield, County of Solano
Pacific Gas and Electric Company (“PG&E” or “the Company”) hereby submits notice
pursuant to General Order (G.O.) 131-D, Section XI, Subsection B.4, of the
construction of facilities that are exempt from a Permit to Construct.
Purpose
This advice letter provides a copy of the Notice of Proposed Construction (Attachment
I) and the Notice Distribution List, which comply with the noticing requirements found in
G.O. 131-D, Section XI.
Background
To maintain safe and reliable electric service in the City of Fairfield, PG&E is proposing
to remove three existing manually-operated transmission switches and three existing
wood poles on this power line, and will replace these facilities with three new
Supervisory Control and Data Acquisition (SCADA) switches, one new weathered steel
engineered direct embedded pole (EDEP), one new weathered tubular steel pole (TSP)
with a concrete foundation, and one new weathered light duty steel pole (LDSP). The
new EDEP will be located approximately 125 feet south of Mangels Boulevard and
1,275 feet northeast of the intersection of Southlake Drive with Mangels Boulevard. The
new TSP will be located near the southerly terminus of Via de Bella. The new LDSP will
be located approximately 70 feet northeast of the southerly terminus of Via de Bella.
Two new SCADA switches will be installed on the new TSP and one new SCADA
switch will be installed on the new EDEP. The new EDEP will be approximately nine
feet taller than the existing wood pole; the new TSP will be approximately 13 feet taller
than the existing wood pole; and the new LDSP will be approximately 25 feet taller than
the existing wood pole. The taller poles are needed to comply with California Public
Utilities Commission (CPUC) General Order (GO) 95 minimum ground to conductor
- Page 1 -
Advice No. 5455-E
-2-
December 26, 2018
clearance requirements. Construction is tentatively scheduled to begin in March 2019 or
as soon as practicable after project approval. Construction will be completed in the
second quarter of 2019, or as soon as possible after construction begins.
CPUC General Order 131-D, Section III, Subsection B.1, exempts projects meeting
specific conditions from the CPUC’s requirement to file an application requesting
authority to construct. The Company believes this project qualifies for the following
exemption(s),
g. “power line facilities or substations to be located in an existing franchise, roadwidening setback easement, or public utility easement; or in a utility corridor
designated, precisely mapped and officially adopted pursuant to law by federal,
state, or local agencies for which a final Negative Declaration or EIR [Environmental
Impact Report] finds no significant unavoidable environmental impacts.”
This filing will not cause the withdrawal of service, or conflict with any other rate
schedule or rule.
Protests
Anyone wishing to protest this filing may do so by filing a protest with the CPUC and the
Company by January 15, 2019, which is 20 days after the date of this filing. Protests
should be mailed to the following address:
CPUC Energy Division
ED Tariff Unit
505 Van Ness Avenue
San Francisco, California 94102
Facsimile: (415) 703-2200
E-Mail: EDTariffUnit@cpuc.ca.gov
Copies of protests also should be mailed to the attention of the Director, Energy
Division, Room 4004, at the address show above.
The protest also should be sent via U.S. mail (and by facsimile and electronically, if
possible) to PG&E at the address shown below on the same date it is mailed or
delivered to the Commission:
David T. Kraska
Attorney, Law Department
Pacific Gas and Electric Company
P.O. Box 7442
San Francisco, California 94120
Facsimile: (415) 973-0516
- Page 2 -
Advice No. 5455-E
-3-
December 26, 2018
Erik Jacobson
Director, Regulatory Relations
Pacific Gas and Electric Company
P.O. Box 770000, Mail Code B13U
San Francisco, California 94177
Facsimile: (415) 973-3582
E-Mail: PGETariffs@pge.com
Persons or groups may protest the proposed construction if they believe that the
Company has incorrectly applied for an exemption or that the conditions set out in
Section III.B.2 of G.O. 131-D exist.
Public Comment
Individuals or groups who do not file an official protest may still submit a comment on
the request to the Energy Division at the address noted above, referencing Advice
Letter 5455-E.
Effective Date
The Company requests that this Tier 2 advice filing become effective on January 25,
2019, which is 30 days after the date of filing. (In accordance with G.O. 131-D,
construction will not begin until 45 days after notice is first published.)
Notice
A copy of this advice letter is being sent electronically and via U.S. Mail to parties
shown on the attached list, including the parties listed in G.O. 131-D, Section XI,
Paragraphs B.1 and B.2. These parties are identified in the “Notice Distribution List”
included in Attachment I.
All electronic approvals should be sent to e-mail
PGETariffs@pge.com. Advice letter filings can also be accessed electronically at
http://www.pge.com/tariffs/.
/S/
Erik Jacobson
Director, Regulatory Relations
cc: Parties Listed in G.O. 131-D, Paragraphs B.1 and B.2
Attachments
- Page 3 -
ADVICE LETTER
SUMMARY
ENERGY UTILITY
MUST BE COMPLETED BY UTILITY (Attach additional pages as needed)
Company name/CPUC Utility No.: Pacific Gas and Electric Company (ID U39 E)
Utility type:
ELC
GAS
PLC
✔
HEAT
ELC = Electric
PLC = Pipeline
WATER
Contact Person: Yvonne Yang
Phone #: (415) 973-2094
E-mail: PGETariffs@pge.com
E-mail Disposition Notice to: Yvonne.Yang@pge.com
EXPLANATION OF UTILITY TYPE
GAS = Gas
WATER = Water
HEAT = Heat
(Date Submitted / Received Stamp by CPUC)
Tier Designation: 2
Advice Letter (AL) #: 5455-E
Subject of AL: Submits Notice of Construction, Pursuant to General Order 131-D, for the Construction of Cordelia #2
60kV Power Line Tap Switch Replacement Project, in the City of Fairfield, County of Solano
Keywords (choose from CPUC listing): Compliance, Power Lines, G.O. 131-D
AL Type:
Monthly
Quarterly
Annual ✔ One-Time
Other:
If AL submitted in compliance with a Commission order, indicate relevant Decision/Resolution #:
N/A
Does AL replace a withdrawn or rejected AL? If so, identify the prior AL: No
Summarize differences between the AL and the prior withdrawn or rejected AL: N/A
Yes
✔ No
N/A
N/A
Yes
✔ No
1/25/19
No. of tariff sheets: N/A
Estimated system annual revenue effect (%): N/A
Estimated system average rate effect (%): N/A
When rates are affected by AL, include attachment in AL showing average rate effects on customer classes
(residential, small commercial, large C/I, agricultural, lighting).
Tariff schedules affected:
N/A
Service affected and changes proposed1: N/A
Pending advice letters that revise the same tariff sheets: N/A
1
Discuss in AL if more space is needed.
Clear Form
- Page 4 -
Protests and all other correspondence regarding this AL are due no later than 20 days after the date
of this submittal, unless otherwise authorized by the Commission, and shall be sent to:
CPUC, Energy Division
Attention: Tariff Unit
505 Van Ness Avenue
San Francisco, CA 94102
Email: EDTariffUnit@cpuc.ca.gov
Name: Erik Jacobson, c/o Megan Lawson
Title: Director, Regulatory Relations
Utility Name: Pacific Gas and Electric Company
Address: 77 Beale Street, Mail Code B13U
City: San Francisco
Zip: 94177
State: California
Telephone (xxx) xxx-xxxx: (415) 973-1877
Facsimile (xxx) xxx-xxxx: (415) 973-3582
Email: PGETariffs@pge.com
Name:
Title:
Utility Name:
Address:
City:
State: District of Columbia
Telephone (xxx) xxx-xxxx:
Facsimile (xxx) xxx-xxxx:
Email:
Zip:
Clear Form
- Page 5 -
Attachment I
NOTICE OF PROPOSED CONSTRUCTION
Para más detalles llame 1-800-660-6789
PROJECT NAME: CORDELIA #2 60KV POWER LINE TAP SWITCH REPLACEMENT PROJECT (City of
Fairfield, PM 74012457)
ADVICE LETTER NUMBER: 5455-E
Proposed Project: To maintain safe and reliable electric service in the City of Fairfield, Pacific Gas and Electric
Company (PG&E) is proposing to remove three existing manually-operated transmission switches and three existing
wood poles on this power line, and will replace these facilities with three new Supervisory Control and Data
Acquisition (SCADA) switches, one new weathered steel engineered direct embedded pole (EDEP), one new
weathered tubular steel pole (TSP) with a concrete foundation, and one new weathered light duty steel pole (LDSP).
The new EDEP will be located approximately 125 feet south of Mangels Boulevard and 1,275 feet northeast of the
intersection of Southlake Drive with Mangels Boulevard. The new TSP will be located near the southerly terminus of
Via de Bella. The new LDSP will be located approximately 70 feet northeast of the southerly terminus of Via de Bella.
Two new SCADA switches will be installed on the new TSP and one new SCADA switch will be installed on the new
EDEP. The new EDEP will be approximately nine feet taller than the existing wood pole; the new TSP will be
approximately 13 feet taller than the existing wood pole; and the new LDSP will be approximately 25 feet taller than
the existing wood pole. The taller poles are needed to comply with California Public Utilities Commission (CPUC)
General Order (GO) 95 minimum ground to conductor clearance requirements. Construction is tentatively scheduled
to begin in March 2019 or as soon as practicable after project approval. Construction will be completed in the second
quarter of 2019, or as soon as possible after construction begins.
Exemption from CPUC Permit Requirement: CPUC General Order 131-D, Section III, Subsection B.1, a utility
from the CPUC’s requirement to file an application requesting authority to construct if a project meets specific
conditions. This project qualifies for the following exemption:
g.
“power line facilities or substations to be located in an existing franchise, road-widening setback easement, or
public utility easement; or in a utility corridor designated, precisely mapped and officially adopted pursuant to
law by federal, state, or local agencies for which a final Negative Declaration or EIR [Environmental Impact
Report] finds no significant unavoidable environmental impacts.”
Additional Project Information: To obtain further information on the proposed project, please call PG&E’s Project
Information Line at (415) 973-5530.
Public Review Process: Individuals or groups may protest the proposed construction if they believe that PG&E has
incorrectly applied for an exemption or that the conditions set out in Section III.B.2 of General Order 131-D exist;
a.
b.
c.
There is reasonable possibility that the activity may have an impact on an environmental resource of hazardous
or critical concern where designated, precisely mapped and officially adopted pursuant to law by federal, state,
or local agencies; or
The cumulative impact of successive projects of the same type in the same place, over time, is significant; or
There is a reasonable possibility that the activity will have a significant effect on the environment due to unusual
circumstances.
Protests should include the following:
1.
2.
3.
4.
Your name, mailing address and daytime telephone number.
Reference to the CPUC Advice Letter Number and Project Name.
A clear description of the reason for the protest.
Whether you believe that evidentiary hearings are necessary to resolve factual disputes.
Protests for this project must be filed by January 15, 2019 at the following address:
Director, Energy Division
ED Tariff Unit
California Public Utilities Commission
505 Van Ness Avenue, Fourth Floor
San Francisco, California 94102
With a copy mailed to:
David Kraska, Law Department
Pacific Gas and Electric Company
P.O. Box 7442
San Francisco, California 94120
PG&E must respond within five business days of receipt and serve its response on each protestant and the Energy
Division. Within 30 days after PG&E has submitted its response, the CPUC Executive Director will send you a copy
of an Executive Resolution granting or denying PG&E’s request and stating the reasons for the decision.
Assistance in Filing a Protest: If you need assistance in filing a protest, contact the CPUC Public Advisor:
email: public.advisor@cpuc.ca.gov or call: 1-866-849-8390 (toll-free), or (415) 703-2074, or TTY (415) 703-5258.
(P. No. 5526487 / SAP Order No. 74012457 / MWC 94)
- Page 6 -
Public Comment: Even if you do not want to file an official protest, you may still comment on the request. To do
so, send your comments to the Energy Division at the address noted above. Please reference Advice Letter 5455-E.
- Page 7 -
Notice Distribution List
CORDELIA #2 60KV POWER LINE TAP SWITCH REPLACEMENT PROJECT (City
of Fairfield, PM 74012457)
Advice 5455-E
Energy Commission
Mr. Drew Bohan, Executive Director
California Energy Commission
1516 Ninth Street, Mail Stop 39
Sacramento, California 95814
Drew.Bohan@energy.ca.gov
Ms. Courtney Smith, Chief Deputy Director
California Energy Commission
1516 Ninth Street, Mail Stop 39
Sacramento, California 95814
Courney.Smith@energy.ca.gov
California Department of Fish and Wildlife
Ms. Karen Weiss, Senior Environmental Scientist Supervisor
California Department of Fish and Wildlife, Bay Delta Region (3)
2825 Cordelia Road, Suite 100
Fairfield, CA 94534
Karen.Weiss@wildlife.ca.gov
City of Fairfield
Mr. Dave Feinstein, Planning Manager
City of Fairfield
Community Development Department, Planning Division
1000 Webster Street
Fairfield, CA 94533
dfeinstein@fairfield.ca.gov
Newspaper
Daily Republic
- Page 8 -
PG&E Gas and Electric Advice
Advice Submittal List
AT&T
Albion Power Company
Alcantar & Kahl LLP
Alta Power Group, LLC
Anderson & Poole
Atlas ReFuel
BART
Barkovich & Yap, Inc.
Braun Blaising Smith Wynne
P.C. CalCom Solar
California Cotton Ginners & Growers Assn
California Energy Commission
California Public Utilities Commission
California State Association of Counties
Calpine
Casner, Steve
Cenergy Power
Center for Biological Diversity
City of Palo Alto
City of San Jose
Clean Power Research
Coast Economic Consulting
Commercial Energy
County of Tehama - Department of Public
Works
Crossborder Energy
Crown Road Energy, LLC
Davis Wright Tremaine LLP
Day Carter Murphy
Dept of General Services
Don Pickett & Associates, Inc.
Douglass & Liddell
Downey & Brand
East Bay Community Energy
Ellison Schneider & Harris LLP
Energy Management Service
Evaluation + Strategy for Social
Innovation
GenOn Energy, Inc.
Goodin, MacBride, Squeri, Schlotz &
Ritchie
Green Charge Networks
Green Power Institute
Hanna & Morton
ICF
International Power Technology
Intestate Gas Services, Inc.
Kelly Group
Ken Bohn Consulting
Keyes & Fox LLP
Leviton Manufacturing Co., Inc.
Linde
Los Angeles County Integrated Waste
Management Task Force
Los Angeles Dept of Water & Power
MRW & Associates
Manatt Phelps Phillips
Marin Energy Authority
McKenzie & Associates
Modesto Irrigation District
Morgan Stanley
NLine Energy, Inc.
NRG Solar
Office of Ratepayer Advocates
OnGrid Solar
Pacific Gas and Electric Company
Pioneer Community Energy
Praxair
Regulatory & Cogeneration Service, Inc.
SCD Energy Solutions
SCE
SDG&E and SoCalGas
SPURR
San Francisco Water Power and Sewer
Seattle City Light
Sempra Utilities
Southern California Edison Company
Southern California Gas Company
Spark Energy
Sun Light & Power
Sunshine Design
Tecogen, Inc.
TerraVerde Renewable Partners
Tiger Natural Gas, Inc.
TransCanada
Troutman Sanders LLP
Utility Cost Management
Utility Power Solutions
Utility Specialists
Verizon
Water and Energy Consulting
Wellhead Electric Company
Western Manufactured Housing
Communities Association (WMA)
Yep Energy
- Page 9 -