Details for: 3986-E (Part 1 of 1).pdf


Click on the image for full size preview

Document data

Gary A. Stern, Ph.D.
Managing Director, State Regulatory Operations

April 12, 2019
ADVICE 3986-E
(U 338-E)
PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
ENERGY DIVISION
Exemption of Power Factor Adjustment Charge to Certain
Customers

SUBJECT:

Southern California Edison Company (SCE) hereby submits for approval by the
California Public Utilities Commission (Commission) the following changes to its tariffs.
The revised tariff sheets are listed on Attachment A and are attached hereto.
PURPOSE
The purpose of this advice letter is to modify various rate schedules to exempt certain
customer generators (i.e., wholesale generator) from the Power Factor Adjustment
(PFA) charge as further discussed below.
BACKGROUND
SCE as a Transmission Provider1 requires reactive power to control system voltage for
efficient and reliable operation of an alternating current (AC) transmission system. At
times, Transmission Providers need generators to either supply or consume reactive
power to maintain adequate system voltage.2 Consistent with Federal Energy
Regulatory Commission (FERC) Order No. 827, SCE requires new generators to be

1

2

Transmission Provider shall mean the public utility (or its designated agent) that owns,
controls, or operates transmission or distribution facilities used for the transmission of
electricity in interstate commerce and provides transmission service under the Tariff. The
term Transmission Provider should be read to include the Transmission Owner when the
Transmission Owner is separate from the Transmission Provider.
Tariff shall mean the Transmission Provider's Tariff through which open access
transmission service and Interconnection Service are offered, as filed with FERC, and as
amended or supplemented from time to time, or any successor tariff.
FERC Order 827 p. 5 - https://www.ferc.gov/whats-new/comm-meet/2016/061616/E-1.pdf.

P.O. Box 800

8631 Rush Street

Rosemead, California 91770

(626) 302-9645

Fax (626) 302-6396





- Page 1 -

ADVICE 3986-E (U 338-E) -2- April 12, 2019 designed such that they can produce or consume volt-ampere reactive (VARs),3 specifically so that they can help maintain system voltage when conditions warrant. Additionally, consistent with the North American Electric Reliability Council (NERC) VAR-002-4 standard, SCE provides many of its generation customers a Voltage and VAR schedule during the commissioning process of generation plants that connect to its transmission system. The Voltage and VAR schedule provides generator operators with guidance on what voltage range to maintain, and in what manner the plant must produce or consume VARs to support transmission system voltages. The ability of generators to maintain system voltage within allowable limits is essential to system reliability. Pursuant to SCE’s FERC Standard Large Generator Interconnection Agreement (LGIA), wholesale generators are required to “maintain a composite power delivery at continuous rated power output at the terminals of the Electric Generating Unit at a power factor within the range of 0.95 leading to 0.90 lagging, unless the CAISO has established different requirements that apply to all generators in the Balancing Authority Area on a comparable basis.” This design criteria is required to enable generators to help maintain acceptable system voltage when real-time conditions warrant. Despite the identified need for generators to occasionally produce or consume VARs to help maintain acceptable system voltage, several of SCE’s tariff’s currently require generator owners to pay a PFA charge ($/kVAR) based on the maximum VAR demand observed in a billing period, even if they are consuming VARs in order to meet their Voltage and VAR schedule. This causes an apparent conflict between the transmission system’s need for generator-assisted voltage regulation and SCE’s tariffs that require SCE to charge customers a PFA fee for providing this voltage regulation. In an effort to address this conflict, SCE is proposing to exempt those customers that are obligated to comply with SCE’s Voltage and VAR schedules from the PFA charge when the following conditions are met: • • 3 The generator operator is operating the plant in accordance with the plant’s published Voltage and VAR schedule, and The generator operator has requested an exemption. This request should include the name, address, and telephone number of the party requesting the exemption. VAR is a unit by which reactive power is expressed in an AC electric power system. Reactive power exists in an AC circuit when the current and voltage are not in phase.
- Page 2 -

ADVICE 3986-E (U 338-E) -3- April 12, 2019 PROPOSED TARIFF CHANGES The following tariffs have been revised and include modifications to the Power Factor Adjustment Special Condition as shown below. Underlined text indicates proposed language. • • • • • • • • Schedule TOU-GS-3, Time-of-Use - General Service - Demand Metered Schedule TOU-GS-3-RTP, - Time-of-Use - General Service – Large, Real Time Pricing Schedule TOU-GS-3-SOP, Time-of-Use - General Service - Super Off Peak Demand Metered Schedule TOU-8, Time-of-Use - General Service – Large Schedule TOU-8-RBU, Time-of-Use - General Service – Large - Reliability Back-Up Service Schedule TOU-8-RTP, - Time-of-Use - General Service – Large, Real Time Pricing Schedule TOU-8-RTP-S, Time-of-Use General Service – Large, Real Time Pricing, Standby; Schedule TOU-8-S, Time-of-Use General Service – Large - Standby, and Special Condition: Power Factor Adjustment: The customer’s bill will be increased each month for power factor by the amount shown in the Rates section above for service metered and delivered at the applicable voltage level, based on the per kilovar of maximum reactive demand imposed by SCE. The maximum reactive demand shall be the highest measured maximum average kilovar demand indicated or recorded by metering during any 15 minute metered interval in the month. The kilovars shall be determined to the nearest unit. A device will be installed on each kilovar meter to prevent reverse operation of the meter. Interconnection Customers who have entered into a FERC Large Generation Interconnection Agreement with SCE and who are otherwise obligated to comply with SCE’s Voltage and VAR schedule that requires the Interconnection Customer to operate its facility in a manner that maintains system voltage within allowable limits, shall be exempt from the Power Factor Adjustment provided that the Interconnection Customer is in compliance with all valid SCE voltage orders. An Interconnection Customer shall mean the entity that interconnects its generating facility with SCE’s transmission system. No cost information is required for this advice letter.
- Page 3 -

ADVICE 3986-E (U 338-E) -4- April 12, 2019 This advice letter will not increase any rate or charge, cause the withdrawal of service, or conflict with any other schedule or rule. TIER DESIGNATION Pursuant to General Order (GO) 96-B, Energy Industry Rule 5.2, this advice letter is submitted with a Tier 2 designation. EFFECTIVE DATE This advice letter will become effective on May 12, 2019, the 30th calendar day after the date submitted. NOTICE Anyone wishing to protest this advice letter may do so by letter via U.S. Mail, facsimile, or electronically, any of which must be received no later than 20 days after the date of this advice letter. Protests should be submitted to: CPUC, Energy Division Attention: Tariff Unit 505 Van Ness Avenue San Francisco, California 94102 E-mail: EDTariffUnit@cpuc.ca.gov Copies should also be mailed to the attention of the Director, Energy Division, Room 4004 (same address above). In addition, protests and all other correspondence regarding this advice letter should also be sent by letter and transmitted via facsimile or electronically to the attention of: Gary A. Stern, Ph.D. Managing Director, State Regulatory Operations Southern California Edison Company 8631 Rush Street Rosemead, California 91770 Telephone (626) 302-9645 Facsimile: (626) 302-6396 E-mail: AdviceTariffManager@sce.com
- Page 4 -

ADVICE 3986-E (U 338-E) -5- April 12, 2019 Laura Genao Managing Director, State Regulatory Affairs c/o Karyn Gansecki Southern California Edison Company 601 Van Ness Avenue, Suite 2030 San Francisco, California 94102 Facsimile: (415) 929-5544 E-mail: Karyn.Gansecki@sce.com There are no restrictions on who may submit a protest, but the protest shall set forth specifically the grounds upon which it is based and must be received by the deadline shown above. In accordance with General Rule 4 of GO 96-B, SCE is serving copies of this advice letter to the interested parties shown on the attached GO 96-B service list. Address change requests to the GO 96-B service list should be directed by electronic mail to AdviceTariffManager@sce.com or at (626) 302-3719. For changes to all other service lists, please contact the Commission’s Process Office at (415) 703-2021 or by electronic mail at Process_Office@cpuc.ca.gov. Further, in accordance with Public Utilities Code Section 491, notice to the public is hereby given by submitting and keeping the advice letter at SCE’s corporate headquarters. To view other SCE advice letters submitted with the Commission, log on to SCE’s web site at https://www.sce.com/wps/portal/home/regulatory/advice-letters. For questions, please contact Darrah Morgan at (626) 302-2086 or by electronic mail at Darrah.Morgan@sce.com. Southern California Edison Company /s/ Gary A. Stern Gary A. Stern, Ph.D. GAS:dm:cm Enclosures
- Page 5 -

ADVICE LETTER SUMMARY ENERGY UTILITY MUST BE COMPLETED BY UTILITY (Attach additional pages as needed) Company name/CPUC Utility No.: Southern California Edison Company (U 338-E) Utility type: ELC GAS PLC HEAT ELC = Electric PLC = Pipeline WATER Contact Person: Darrah Morgan Phone #: (626) 302-2086 E-mail: Darrah.Morgan@sce.com E-mail Disposition Notice to: AdviceTariffManager@sce.com EXPLANATION OF UTILITY TYPE GAS = Gas WATER = Water HEAT = Heat (Date Submitted / Received Stamp by CPUC) Tier Designation: 2 Advice Letter (AL) #: 3986-E Subject of AL: Exemption of Power Factor Adjustment Charge to Certain Customers Keywords (choose from CPUC listing): AL Type: Monthly Quarterly Annual One-Time Other: If AL submitted in compliance with a Commission order, indicate relevant Decision/Resolution #: Does AL replace a withdrawn or rejected AL? If so, identify the prior AL: Summarize differences between the AL and the prior withdrawn or rejected AL: Confidential treatment requested? Yes No If yes, specification of confidential information: Confidential information will be made available to appropriate parties who execute a nondisclosure agreement. Name and contact information to request nondisclosure agreement/ access to confidential information: Resolution required? Yes No Requested effective date: 5/12/19 No. of tariff sheets: -13- Estimated system annual revenue effect (%): Estimated system average rate effect (%): When rates are affected by AL, include attachment in AL showing average rate effects on customer classes (residential, small commercial, large C/I, agricultural, lighting). Tariff schedules affected: See Attachment A Service affected and changes proposed1: Pending advice letters that revise the same tariff sheets: 3977-E 1 Discuss in AL if more space is needed. Clear Form
- Page 6 -

Protests and all other correspondence regarding this AL are due no later than 20 days after the date of this submittal, unless otherwise authorized by the Commission, and shall be sent to: CPUC, Energy Division Attention: Tariff Unit 505 Van Ness Avenue San Francisco, CA 94102 Email: EDTariffUnit@cpuc.ca.gov Name: Gary A. Stern, Ph.D. Title: Managing Director, State Regulatory Operations Utility Name: Southern California Edison Company Address: 8631 Rush Street City: Rosemead Zip: 91770 State: California Telephone (xxx) xxx-xxxx: (626) 302-9645 Facsimile (xxx) xxx-xxxx: (626) 302-6396 Email: advicetariffmanager@sce.com Name: Laura Genao c/o Karyn Gansecki Title: Managing Director, State Regulatory Affairs Utility Name: Southern California Edison Company Address: 601 Van Ness Avenue, Suite 2030 City: San Francisco State: California Zip: 94102 Telephone (xxx) xxx-xxxx: Facsimile (xxx) xxx-xxxx: (415) 929-5544 Email: karyn.gansecki@sce.com Clear Form
- Page 7 -

ENERGY Advice Letter Keywords Affiliate Direct Access Preliminary Statement Agreements Disconnect Service Procurement Agriculture ECAC / Energy Cost Adjustment Qualifying Facility Avoided Cost EOR / Enhanced Oil Recovery Rebates Balancing Account Energy Charge Refunds Baseline Energy Efficiency Reliability Bilingual Establish Service Re-MAT/Bio-MAT Billings Expand Service Area Revenue Allocation Bioenergy Forms Rule 21 Brokerage Fees Franchise Fee / User Tax Rules CARE G.O. 131-D Section 851 CPUC Reimbursement Fee GRC / General Rate Case Self Generation Capacity Hazardous Waste Service Area Map Cogeneration Increase Rates Service Outage Compliance Interruptible Service Solar Conditions of Service Interutility Transportation Standby Service Connection LIEE / Low-Income Energy Efficiency Storage Conservation LIRA / Low-Income Ratepayer Assistance Street Lights Consolidate Tariffs Late Payment Charge Surcharges Contracts Line Extensions Tariffs Core Memorandum Account Taxes Credit Metered Energy Efficiency Text Changes Curtailable Service Metering Transformer Customer Charge Customer Owned Generation Mobile Home Parks Name Change Transition Cost Transmission Lines Decrease Rates Non-Core Transportation Electrification Demand Charge Non-firm Service Contracts Transportation Rates Demand Side Fund Nuclear Undergrounding Demand Side Management Oil Pipelines Voltage Discount Demand Side Response PBR / Performance Based Ratemaking Wind Power Deposits Portfolio Withdrawal of Service Depreciation Power Lines Clear Form
- Page 8 -

Public Utilities Commission 3986-E Cal. P.U.C. Sheet No. Title of Sheet Attachment A Cancelling Cal. P.U.C. Sheet No. Revised 66891-E Revised 66892-E Schedule TOU-GS-3 Schedule TOU-GS-3 Revised 66243-E Revised 66776-E Revised 66893-E Revised 66894-E Schedule TOU-GS-3-RTP Schedule TOU-GS-3-RTP Revised 66258-E Revised 66779-E Revised 66258-E Revised 66895-E Schedule TOU-GS-3-SOP Revised 51765-E Revised 66896-E Revised 66897-E Schedule TOU-8 Schedule TOU-8 Revised 66289-E Revised 66289-E Revised 66290-E Revised 66898-E Schedule TOU-8-RBU Revised 53868-E Revised 66899-E Schedule TOU-8-RTP Revised 66320-E Revised 66900-E Schedule TOU-8-RTP-S Revised 66355-E Revised 66901-E Schedule TOU-8-S Revised 66392-E Revised 66902-E Revised 66903-E Table of Contents Table of Contents Revised 66856-E Revised 66859-E 1
- Page 9 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised Cal. PUC Sheet No. Cal. PUC Sheet No. Schedule TOU-GS-3 TIME-OF-USE - GENERAL SERVICE - DEMAND METERED 66891-E 66243-E Sheet 13 (Continued) SPECIAL CONDITIONS (Continued) 5. Maximum Demand: Maximum Demand shall be established for all applicable TOU Periods. The Maximum Demand for each TOU period shall be the measured maximum average kilowatt (kW) input, indicated or recorded by instruments, such as SCE metering, during any 15-minute metered interval, but where applicable, not less than the diversified resistance welder load computed in accordance with the section designated Welder Service in Rule 2. Where the demand is intermittent or subject to violent fluctuations, a 5-minute interval may be used. 6. Billing Demand: The Billing Demand shall be the kW of Maximum Demand, determined to the nearest kW. When applicable, the Time Related Demand (TRD) component shall be for the kW of Maximum Demand recorded during (or established for) each of the TOU Periods, as applicable according to the Customers TOU Option. The Facilities Related Demand (FRD) component shall be for the kW of Maximum Demand recorded during (or established for) the monthly billing period. However, when SCE determines the Customer’s meter will record little or no energy use for extended periods of time or when the Customer’s meter has not recorded a Maximum Demand in the preceding eleven months, the Facilities Related Component of the Demand Charge may be established at 50 percent of the customer’s connected load. Separate Demand Charge(s) for each of the applicable TOU Periods shall be established for each monthly billing period. The Demand Charge for each time period shall be based on the Maximum Demand for that time period occurring during the respective monthly billing period. 7. Voltage Discount: Bundled Service, CCA Service, and Direct Access customers will have the Distribution rate component of the applicable Delivery Service charges reduced by the corresponding Voltage Discount amount for service metered and delivered at the applicable voltage level as shown in the RATES section above. In addition, Bundled Service Customers will have the Utility Generation (UG) rate component of the applicable Generation charges reduced by the corresponding Voltage Discount amount for service metered and delivered at the applicable voltage level as shown in the RATES section. 8. Power Factor Adjustment: The Customer’s bill will be increased each month for power factor by the amount shown in the Rates section above for service metered and delivered at the applicable voltage level, based on the per kilovar of maximum reactive demand imposed by SCE. The maximum reactive demand shall be the highest measured maximum average kilovar demand indicated or recorded by metering during any 15 minute metered interval in the month. The kilovars shall be determined to the nearest unit. A device will be installed on each kilovar meter to prevent reverse operation of the meter. Interconnection Customers who have entered into a FERC Large Generation Interconnection Agreement with SCE and who are otherwise obligated to comply with SCE’s Voltage and VAR schedule that requires the Interconnection Customer to operate its facility in a manner that maintains system voltage within allowable limits, shall be exempt from the Power Factor Adjustment provided that the Interconnection Customer is in compliance with all valid SCE voltage orders. (N) | | | | (N) (Continued) (To be inserted by utility) Advice 3986-E Decision 13D7 Issued by R.O. Nichols Senior Vice President (To be inserted by Cal. PUC) Date Filed Apr 12, 2019 Effective Resolution
- Page 10 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised Cal. PUC Sheet No. Cal. PUC Sheet No. Schedule TOU-GS-3 TIME-OF-USE - GENERAL SERVICE - DEMAND METERED 66892-E 66776-E Sheet 14 (Continued) SPECIAL CONDITIONS (Continued) 8. Power Factor Adjustment: (Continued) (N) An Interconnection Customer shall mean the entity that interconnects its generating facility with SCE’s transmission system. 9. Temporary Discontinuance of Service: When the use of energy is seasonal or intermittent, no adjustments will be made for a temporary discontinuance of service. Any Customer prior to resuming service within twelve months after such service was discontinued will be required to pay all charges which would have been billed if service had not been discontinued. 10. (N) (N) Customer-Owned Electrical Generating Facilities: a. Where Customer-owned electrical Generating Facilities are used to meet a part or all of the Customer's electrical requirements, service shall be provided concurrently under the terms and conditions of Schedule S and this Schedule. Parallel operation of such generating facilities with SCE’s electrical system is permitted. A generation interconnection agreement is required for such operation. b. Customer-owned electrical Generating Facilities used solely for auxiliary, emergency, or standby purposes (auxiliary/emergency generating facilities) to serve the Customer's load during a period when SCE’s service is unavailable and when such load is isolated from the service of SCE are not subject to Schedule S. However, upon approval by SCE, momentary parallel operation may be permitted to allow the Customer to test the auxiliary/emergency generating facilities. A Momentary Parallel Generation Contract is required for this type of service. 11. California Alternate Rates for Energy (CARE) Discount: Customers who meet the definition of a Group Living Facility, Agricultural Employee Housing, or Migrant Farm Worker Housing Center as defined in Preliminary Statement, Part O, Section 3, qualify for a 28.2 percent discount off of their electric bill prior to application of the Public Utilities Commission Reimbursement Fee (PUCRF) and any applicable user fees, taxes, and late payment charges. Eligible CARE Customers are required to pay the PUCRF and any applicable user fees, taxes, and late payment charges in full. In addition, eligible CARE Customers are exempt from paying the CARE Surcharge of $0.00518 per kWh and the Department of Water Resources Board Charge of $0.00503 per kWh. The 28.2 percent discount in addition to these exemptions results in an average effective CARE Discount of 32.5 percent. An application and eligibility declaration, as defined in Preliminary Statement, Part O, Section 3, is required for service under this Special Condition. Eligible Customers shall have the CARE Discount applied to this Schedule commencing no later than one billing period after receipt and approval of the Customer's application by SCE. Customers may be rebilled on the applicable rate schedule for periods in which they do not meet the eligibility requirements for the CARE discount as defined in Preliminary Statement, Part O, Section 3. 12. Removal From Schedule: Customers receiving service under this Schedule whose monthly Maximum Demand has registered 200 kW or less for 12 consecutive months shall be changed to an applicable rate schedule effective with the date the Customer became ineligible for service under this Schedule. (Continued) (To be inserted by utility) Advice 3986-E Decision 14D6 Issued by R.O. Nichols Senior Vice President (To be inserted by Cal. PUC) Date Filed Apr 12, 2019 Effective Resolution
- Page 11 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised Schedule TOU-GS-3-RTP GENERAL SERVICE - LARGE REAL TIME PRICING (Continued) Cal. PUC Sheet No. Cal. PUC Sheet No. 66893-E 66258-E Sheet 7 SPECIAL CONDITIONS (Continued) 5. Real Time Pricing: As used in this Schedule, Real Time Pricing is the practice of continuously varying prices to Customers to reflect simulated hourly variations in the marginal costs of generating electricity. 6. Voltage Discount: Bundled Service Customers receiving service at 220 kV will have the Distribution rate component of the applicable Delivery Service charges reduced by the corresponding Voltage Discount amount for service metered and delivered at the applicable voltage level as shown in the RATES section above. In addition, Bundled Service Customers will have the Utility Generation (UG) rate component of the applicable Generation charges reduced by the corresponding Voltage Discount amount for service metered and delivered at the applicable voltage level as shown in the RATES section. 7. Power Factor Adjustment: The customer’s bill will be increased each month for power factor by the amount shown in the Rates section above for service metered and delivered at the applicable voltage level, based on the per kilovar of maximum reactive demand imposed by SCE. The maximum reactive demand shall be the highest measured maximum average kilovar demand indicated or recorded by metering during any 15 minute metered interval in the month. The kilovars shall be determined to the nearest unit. A device will be installed on each kilovar meter to prevent reverse operation of the meter. Interconnection Customers who have entered into a FERC Large Generation Interconnection Agreement with SCE and who are otherwise obligated to comply with SCE’s Voltage and VAR schedule that requires the Interconnection Customer to operate its facility in a manner that maintains system voltage within allowable limits, shall be exempt from the Power Factor Adjustment provided that the Interconnection Customer is in compliance with all valid SCE voltage orders. An Interconnection Customer shall mean the entity that interconnects its generating facility with SCE’s transmission system. 8. The daily maximum temperature, as recorded by the National Weather Service, at its Downtown Los Angeles site, will be used to determine the hourly rates for the following day according to this Schedule. It is the responsibility of the Customers to acquire the daily maximum temperature at the Los Angeles Downtown site. SCE is not required to provide the daily maximum temperature. In the event that data is unavailable from Downtown LA as the primary source, data collected by the National Weather Service from Long Beach Airport shall be used. Where data is not available from either site, SCE shall enact its procedure for emergency data collection in order to provide substitute temperature data. 9. (N) | | | | | | | | (N) Temporary Discontinuance of Service: When the use of energy is seasonal or intermittent, no adjustments will be made for a temporary discontinuance of service. Any Customer prior to resuming service within twelve months after such service was discontinued will be required to pay all charges which would have been billed if service had not been discontinued. (L) (Continued) (To be inserted by utility) Advice 3986-E Decision 7D7 Issued by R.O. Nichols Senior Vice President (To be inserted by Cal. PUC) Date Filed Apr 12, 2019 Effective Resolution
- Page 12 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised Schedule TOU-GS-3-RTP GENERAL SERVICE - LARGE REAL TIME PRICING (Continued) Cal. PUC Sheet No. Cal. PUC Sheet No. 66894-E 66779-E 66258-E Sheet 8 SPECIAL CONDITIONS (Continued) Customer-Owned Electrical Generating Facilities: (T) a. Where Customer-owned electrical Generating Facilities are used to meet a part or all of the Customer’s electrical requirements, service shall be provided concurrently under the terms and conditions of Schedule S and this Schedule. Parallel operation of such Generating Facilities with SCE’s electrical system is permitted. A generation interconnection agreement is required for such operation. (L) | | | (L) b. 10. Customer-owned electrical Generating Facilities used solely for auxiliary, emergency, or standby purposes (auxiliary/emergency Generating Facilities) to serve the Customer’s load during a period when SCE’s service is unavailable and when such load is isolated from the service of SCE are not subject to Schedule S. However, upon approval by SCE, momentary parallel operation may be permitted to allow the Customer to test the auxiliary/emergency generating facilities. A Momentary Parallel Generation Contract is required for this type of service. 11. California Alternate Rates for Energy (CARE) Discount: Customers who meet the definition of a Group Living Facility, Agricultural Employee Housing, or Migrant Farm Worker Housing Center as defined in Preliminary Statement, Part O, Section 3, qualify for a 28.2 percent discount off of their electric bill prior to application of the Public Utilities Commission Reimbursement Fee (PUCRF) and any applicable user fees, taxes, and late payment charges. Eligible CARE Customers are required to pay the PUCRF and any applicable user fees, taxes, and late payment charges in full. In addition, eligible CARE Customers are exempt from paying the CARE Surcharge of $0.00518 per kWh and the Department of Water Resources Board Charge of $0.00503 per kWh. The 28.2 percent discount in addition to these exemptions results in an average effective CARE Discount of 32.5 percent. An application and eligibility declaration, as defined in Preliminary Statement, Part O, Section 3, is required for service under this Special Condition. Eligible Customers shall have the CARE Discount applied to this Schedule commencing no later than one billing period after receipt and approval of the Customer's application by SCE. Customers may be rebilled on the applicable rate schedule for periods in which they do not meet the eligibility requirements for the CARE discount as defined in Preliminary Statement, Part O, Section 3. 12. Food Bank Discount: Customers who meet the definition of an Eligible Food Bank as defined in Form 14-984, Declaration of Eligibility for Food Bank Discount, qualify for a 20 percent discount off their electric bill prior to application of the Public Utilities Commission Reimbursement Fee (PUCRF) and any applicable user fees, taxes, and late payment charges. Eligible Food Bank Customers are required to pay the PUCRF and any applicable user fees, taxes, and late payment charges in full. An eligibility declaration, Form 14-984, Declaration of Eligibility for Food Bank Discount, is required for service under this Special Condition. Eligible Customers shall have the Food Bank Discount applied to this Schedule commencing no later than one billing period after receipt and approval of the Customer's declaration of eligibility by SCE. (Continued) (To be inserted by utility) Advice 3986-E Decision 8D7 Issued by R.O. Nichols Senior Vice President (To be inserted by Cal. PUC) Date Filed Apr 12, 2019 Effective Resolution
- Page 13 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised Cal. PUC Sheet No. Cal. PUC Sheet No. Schedule TOU-GS-3-SOP TIME-OF-USE - GENERAL SERVICE SUPER OFF-PEAK - DEMAND METERED (Continued) SPECIAL CONDITIONS (Continued) 66895-E 51765-E Sheet 3 2. Voltage: Service will be supplied at one standard voltage. 3. Maximum Demand: Maximum demands shall be established for the On-Peak, Mid-Peak, and Super Off-Peak Time Periods. The maximum demand for each period shall be the measured maximum average kilowatt input indicated or recorded by instruments, during any 15-minute metered interval, but, where applicable, not less than the diversified resistance welder load computed in accordance with the section designated Welder Service in Rule 2. Where the demand is intermittent or subject to violent fluctuations, a 5-minute interval may be used. 4. Billing Demand: The Billing Demand shall be the kilowatts of Maximum Demand, determined to the nearest kW. The Demand Charge shall include the following billing components. The Time Related Component shall be for the kilowatts of Maximum Demand recorded during (or established for) the monthly billing period for each of the On-Peak, Mid-Peak, and Super OffPeak Time Periods. The Facilities Related Component shall be for the kilowatts of Maximum Demand recorded during (or established for) the monthly billing period. However, when SCE determines the customer's meter will record little or no energy use for extended periods of time or when the customer's meter has not recorded a Maximum Demand in the preceding eleven months, the Facilities Related Component of the Demand Charge may be established at 50 percent of the customer's connected load. Separate Demand Charge(s) for the On-Peak, MidPeak, and Super Off-Peak Time Periods shall be established for each monthly billing period. The Demand Charge for each time period shall be based on the Maximum Demand for that time period occurring during the respective monthly billing period. 5. Voltage Discount: Bundled Service and Direct Access Customers will have the Distribution rate component of the applicable Delivery Service charges reduced by the corresponding Voltage Discount amount for service metered and delivered at the applicable voltage level as shown in the RATES section above. In addition, Bundled Service Customers will have the Utility Generation (UG) rate component of the applicable Generation charges reduced by the corresponding Voltage Discount amount for service metered and delivered at the applicable voltage level as shown in the RATES section. 6. Power Factor Adjustment: The customer’s bill will be increased each month for power factor by the amount shown in the RATES section above for service metered and delivered at the applicable voltage level, based on the per kilovar of maximum reactive demand imposed by SCE. The maximum reactive demand shall be the highest measured maximum average kilovar demand indicated or recorded by metering during any 15 minute metered interval in the month. The kilovars shall be determined to the nearest unit. A device will be installed on each kilovar meter to prevent reverse operation of the meter. Interconnection Customers who have entered into a FERC Large Generation Interconnection Agreement with SCE and who are otherwise obligated to comply with SCE’s Voltage and VAR schedule that requires the Interconnection Customer to operate its facility in a manner that maintains system voltage within allowable limits, shall be exempt from the Power Factor Adjustment provided that the Interconnection Customer is in compliance with all valid SCE voltage orders. An Interconnection Customer shall mean the entity that interconnects its generating facility with SCE’s transmission system. (N) | | | | | | | (N) (Continued) (To be inserted by utility) Advice 3986-E Decision 3D7 Issued by R.O. Nichols Senior Vice President (To be inserted by Cal. PUC) Date Filed Apr 12, 2019 Effective Resolution
- Page 14 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised Cal. PUC Sheet No. Cal. PUC Sheet No. Schedule TOU-8 TIME-OF-USE - GENERAL SERVICE - LARGE 66896-E 66289-E Sheet 22 (Continued) SPECIAL CONDITIONS (Continued) 1. Applicable rate time periods are defined as follows: (Continued) The summer season shall commence at 12:00 a.m. on June 1 and continue until 12:00 a.m. on October 1 of each year. The winter season shall commence at 12:00 a.m. on October 1 and continue until 12:00 a.m. on June 1 of the following year. See Special Condition 11 for Time Periods applicable to Qualifying Facilities. 2. Voltage: Service will be supplied at one standard voltage. 3. Maximum Demand: Maximum demand shall be established for all applicable TOU periods. The Maximum Demand for each TOU period shall be the measured maximum average kilowatt (kW) input indicated or recorded by instruments, such as SCE metering, during any 15-minute metered interval, but where applicable, not less than the diversified resistance welder load computed in accordance with the section designated Welder Service in Rule 2. Where the demand is intermittent or subject to violent fluctuations, a 5-minute interval may be used. 4. Billing Demand: The Billing Demand shall be the kW of Maximum Demand, determined to the nearest kW. When applicable, the Time Related Demand (TRD) component shall be for the kW of Maximum Demand recorded during (or established for) each of the TOU Periods, as applicable according to the Customer’s TOU Option. The Facilities Related Demand (FRD) component shall be for the kW of Maximum Demand recorded during (or established for) the monthly billing period. However, when SCE determines the customer's meter will record little or no energy use for extended periods of time or when the customer's meter has not recorded a Maximum Demand in the preceding eleven months, the Facilities Related Component of the Demand Charge may be established at 50 percent of the customer's connected load. Separate Demand Charge(s) for each of the TOU Periods shall be established for each monthly billing period. The Demand Charge for each TOU period shall be based on the Maximum Demand for that time period occurring during the respective monthly billing period. 5. Power Factor Adjustment: The customer’s bill will be increased each month for power factor by the amount shown in the Rates section above for service metered and delivered at the applicable voltage level, based on the per kilovar of maximum reactive demand imposed by SCE. The maximum reactive demand shall be the highest measured maximum average kilovar demand indicated or recorded by metering during any 15 minute metered interval in the month. The kilovars shall be determined to the nearest unit. A device will be installed on each kilovar meter to prevent reverse operation of the meter. Interconnection Customers who have entered into a FERC Large Generation Interconnection Agreement with SCE and who are otherwise obligated to comply with SCE’s Voltage and VAR schedule that requires the Interconnection Customer to operate its facility in a manner that maintains system voltage within allowable limits, shall be exempt from the Power Factor Adjustment provided that the Interconnection Customer is in compliance with all valid SCE voltage orders. An Interconnection Customer shall mean the entity that interconnects its generating facility with SCE’s transmission system. (N) | | | | | | | (N) (L) (Continued) (To be inserted by utility) Advice 3986-E Decision 22D8 Issued by R.O. Nichols Senior Vice President (To be inserted by Cal. PUC) Date Filed Apr 12, 2019 Effective Resolution
- Page 15 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised Cal. PUC Sheet No. Cal. PUC Sheet No. Schedule TOU-8 TIME-OF-USE - GENERAL SERVICE - LARGE 66897-E 66289-E 66290-E Sheet 23 (Continued) SPECIAL CONDITIONS (Continued) 6. Critical Peak Pricing: Critical Peak Pricing (CPP) is an event-based pricing option which provides bill credits in the Summer Season from 4:00 p.m. to 9:00 p.m. during CPP Non-Event Credit Periods and incremental bill charges for load served by SCE during CPP Event Charge Periods. No CPP credits will be provided for exported generation, i.e., energy produced and exported by the customer’s generating facility during CPP Non-Event Credit Periods. a. (L) | | | | (L) CPP Events: SCE may, at its discretion, call a CPP Event any non-holiday weekday. CPP Events will be called based on any one of the following criteria: (1) (2) (3) (4) California Independent System Operator (CAISO) Alert or Warning Notice, Forecasts of SCE system emergencies – may be declared at the generation, transmission, or distribution circuit level Forecasts of extreme or unusual temperature conditions impacting system demand Day-ahead load and/or price forecasts. b. Number of CPP Events: There will be 12 CPP Events per calendar year. c. Customers enrolled in a CPP Option under another Schedule who are moved to this Schedule due to a permanent change in operating conditions and have a change in their Maximum Demand will be enrolled in Option D-CPP or B-CPP of this Schedule, as applicable, or may elect another applicable Option. d. Notification of a CPP Event: SCE will notify Customers of a CPP Event via SCE’s notification system. Customers are responsible for providing SCE with contact information consisting of a telephone number, electronic mail address, and/or SMS text number for notification of Events. Customers are responsible for updating customer contact information as necessary. SCE will begin to notify customers no later than 3:00 p.m. the day before a CPP Event. Customers are responsible for all charges incurred during a CPP Event, even if notice is not received. Customers who fail to provide the necessary contact information prior to CPP Events are responsible for all charges incurred during CPP Events. e. Participation in other Programs: Only Bundled Service Customers shall be served under the CPP of this Schedule. Direct Access, Community Aggregation and Community Choice Aggregation Service Customers are ineligible for CPP of this Schedule. CPP Customers served under this Schedule are eligible for service under Net Energy Metering Schedules. CPP Customers served under this Schedule are not eligible for service under Option E or R of this Schedule. Only Customers dually participating in CPP of this Schedule with another demand response programs prior to October 26, 2018 are grandfathered to continue the existing dual participation. All other Customers served under CPP of this Schedule are not eligible to dually enroll in any demand response program offered by SCE or any thirdparty administered demand response program. (Continued) (To be inserted by utility) Advice 3986-E Decision 23D7 Issued by R.O. Nichols Senior Vice President (To be inserted by Cal. PUC) Date Filed Apr 12, 2019 Effective Resolution
- Page 16 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised Cal. PUC Sheet No. Cal. PUC Sheet No. Schedule TOU-8-RBU TIME-OF-USE - GENERAL SERVICE - LARGE RELIABILITY BACK-UP SERVICE (Continued) SPECIAL CONDITIONS (Continued) 5. 66898-E 53868-E Sheet 5 Power Factor Adjustment: The customer’s bill will be increased each month for power factor by the amount shown in the RATES section above for service metered and delivered at the applicable voltage level, based on the per kilovar of maximum reactive demand imposed on SCE. The maximum reactive demand shall be the highest measured maximum average kilovar demand indicated or recorded by metering during any 15-minute metered interval in the month. The kilovars shall be determined to the nearest unit. A device will be installed on each kilovar meter to prevent reverse operation of the meter. Interconnection Customers who have entered into a FERC Large Generation Interconnection Agreement with SCE and who are otherwise obligated to comply with SCE’s Voltage and VAR schedule that requires the Interconnection Customer to operate its facility in a manner that maintains system voltage within allowable limits, shall be exempt from the Power Factor Adjustment provided that the Interconnection Customer is in compliance with all valid SCE voltage orders. An Interconnection Customer shall mean the entity that interconnects its generating facility with SCE’s transmission system. 6. Temporary Discontinuance of Service. Where the use of energy is seasonal or intermittent, no adjustments will be made for a temporary discontinuance of service. Any customer prior to resuming service within twelve months after such service was discontinued will be required to pay all charges which would have been billed if service had not been discontinued. 7. Parallel Connections. No parallel connection of the main and reliability back-up services shall be permitted. SCE shall control the transfer of the customer’s load from the main service to the reliability back-up service. 8. Contracts. A contract is required for service under this Schedule. In addition to the reliability back-up service contract, the customer shall have executed an added facilities contract for the reliability back-up service facilities. 9. (N) | | | | | | | (N) Removal From Schedule. Customers receiving service under this Schedule who become ineligible for service under Schedule TOU-8, TOU-8-S, or TOU-8-RTP-S for the main service are, effective with the date of such ineligibility, no longer eligible for service under this Schedule, and may be subject to the termination provision of the added facilities contract for the reliability back-up service facilities. Should the customer elect to terminate its added facilities contract for the reliability back-up service facilities, service under this Schedule shall expire concurrent with the effective date of such termination. (Continued) (To be inserted by utility) Advice 3986-E Decision 5D7 Issued by R.O. Nichols Senior Vice President (To be inserted by Cal. PUC) Date Filed Apr 12, 2019 Effective Resolution
- Page 17 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised Schedule TOU-8-RTP GENERAL SERVICE - LARGE REAL TIME PRICING (Continued) Cal. PUC Sheet No. Cal. PUC Sheet No. 66899-E 66320-E Sheet 12 SPECIAL CONDITIONS (Continued) 5. Real Time Pricing: As used in this Schedule, Real Time Pricing is the practice of continuously varying prices to Customers to reflect simulated hourly variations in the marginal costs of generating electricity. 6. Voltage Discounts: Bundled Service Customers will have the Distribution rate component of the applicable Delivery Service charges reduced by the corresponding Voltage Discount amount for service metered and delivered at the applicable voltage level as shown in the RATES section above. In addition, Customers receiving service at 220 kV will have the Utility Generation (UG) rate component of the applicable Generation Charges for service above 50 kV reduced by the corresponding Voltage Discount amount for service metered and delivered at 220 kV as shown in the RATES section. 7. Power Factor Adjustment: The Customer’s bill will be increased each month for power factor by the amount shown in the Rates section above for service metered and delivered at the applicable voltage level, based on the per kilovar of maximum reactive demand imposed on SCE. The maximum reactive demand shall be the highest measured maximum average kilovar demand indicated or recorded by metering during any 15-minute metered interval in the month. The kilovars shall be determined to the nearest unit. A device will be installed on each kilovar meter to prevent reverse operation of the meter. Interconnection Customers who have entered into a FERC Large Generation Interconnection Agreement with SCE and who are otherwise obligated to comply with SCE’s Voltage and VAR schedule that requires the Interconnection Customer to operate its facility in a manner that maintains system voltage within allowable limits, shall be exempt from the Power Factor Adjustment provided that the Interconnection Customer is in compliance with all valid SCE voltage orders. An Interconnection Customer shall mean the entity that interconnects its generating facility with SCE’s transmission system. 8. Temporary Discontinuance of Service: Where the use of energy is seasonal or intermittent, no adjustments will be made for a temporary discontinuance of service. Any Customer prior to resuming service within twelve months after such service was discontinued will be required to pay all charges which would have been billed if service had not been discontinued. 9. (N) | | | | | | | (N) The daily maximum temperature, as recorded by the National Weather Service, at its Downtown Los Angeles site, will be used to determine the hourly rates for the following day according to this Schedule. It is the responsibility of the Customers to acquire the daily maximum temperature at the Los Angeles Downtown site. SCE is not required to provide the daily maximum temperature. In the event that data is unavailable from Downtown LA as the primary source, data collected by the National Weather Service from Long Beach Airport shall be used. Where data is not available from either site, SCE shall enact its procedure for emergency data collection in order to provide substitute temperature data. (Continued) (To be inserted by utility) Advice 3986-E Decision 12D7 Issued by R.O. Nichols Senior Vice President (To be inserted by Cal. PUC) Date Filed Apr 12, 2019 Effective Resolution
- Page 18 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised Cal. PUC Sheet No. Cal. PUC Sheet No. Schedule TOU-8-RTP-S TIME-OF-USE - GENERAL SERVICE - LARGE REAL TIME PRICING - STANDBY (Continued) SPECIAL CONDITIONS (Continued) 13. 66900-E 66355-E Sheet 23 Power Factor Adjustment: The Customer’s bill will be increased each month for power factor by the amount shown in the RATES section above for service metered and delivered at the applicable voltage level, based on the per kilovar of maximum reactive demand imposed on SCE’s system. The maximum reactive demand shall be the highest measured maximum average kilovar demand indicated or recorded during any 15-minute metered interval in the month. The kilovars shall be determined to the nearest unit. A device will be installed on each kilovar meter to prevent reverse operation of the meter. Interconnection Customers who have entered into a FERC Large Generation Interconnection Agreement with SCE and who are otherwise obligated to comply with SCE’s Voltage and VAR schedule that requires the Interconnection Customer to operate its facility in a manner that maintains system voltage within allowable limits, shall be exempt from the Power Factor Adjustment provided that the Interconnection Customer is in compliance with all valid SCE voltage orders. An Interconnection Customer shall mean the entity that interconnects its generating facility with SCE’s transmission system. 14. The daily maximum temperature, as recorded by the National Weather Service, at its Downtown Los Angeles site, will be used to determine the hourly rates for the following day according to this Schedule. It is the responsibility of the Customers to acquire the daily maximum temperature at the Los Angeles Downtown site. SCE is not required to provide the daily maximum temperature. In the event that data is unavailable from Downtown LA as the primary source, data collected by the National Weather Service from Long Beach Airport shall be used. Where data is not available from either site, SCE shall enact its procedure for emergency data collection in order to provide substitute temperature data. 15. (N) | | | | | | | (N) Threshold Rule Exceptions: a. Individual water agency accounts with demands above 500 kW where 70 percent or more of the water pumped is used for Agricultural Power Service purposes, and other water pumping accounts with demands above 500 kW where 70 percent or more of the water pumped is used for Agricultural Power Service purposes who have signed Form 14-317, Declaration and Rate Election for Water Agencies and Water Pumping Accounts, are not eligible for service under this Schedule. Such accounts must take service on an agricultural and pumping rate schedule and Schedule S. b. Customers with demands above 500 kW who are (1) packing houses that pack only whole fruits or whole vegetables, and associated cold storage on the same Premises as the packing houses; (2) cotton gins; (3) nut hulling and shelling operations; or (4) producing unflavored fluid milk fit for human consumption by way of pasteurization, homogenization, vitaminization or fat standardization that have signed Form 14-927, Affidavit Regarding Eligibility for Agricultural Power Service, are not required to take service under this Schedule and are eligible for service on an applicable agricultural and pumping rate schedule and Schedule S. c. Agricultural Power Service Customers with electric energy and service used on the same Premises where the Customer produces agricultural or horticultural products, including poultry and livestock, are not required to take service under this Schedule and are eligible for service on an applicable agricultural and pumping rate schedule. (Continued) (To be inserted by utility) Advice 3986-E Decision 23D7 Issued by R.O. Nichols Senior Vice President (To be inserted by Cal. PUC) Date Filed Apr 12, 2019 Effective Resolution
- Page 19 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised Cal. PUC Sheet No. Cal. PUC Sheet No. Schedule TOU-8-S TIME-OF-USE - GENERAL SERVICE - LARGE STANDBY (Continued) SPECIAL CONDITIONS (Continued) 12. 66901-E 66392-E Sheet 27 Power Factor Adjustment: The customer’s bill will be increased each month for power factor by the amount shown in the RATES section above for service metered and delivered at the applicable voltage level, based on the per kilovar of maximum reactive demand imposed on SCE’s system. The maximum reactive demand shall be the highest measured maximum average kilovar demand indicated or recorded during any 15-minute metered interval in the month. The kilovars shall be determined to the nearest unit. A device will be installed on each kilovar meter to prevent reverse operation of the meter. Interconnection Customers who have entered into a FERC Large Generation Interconnection Agreement with SCE and who are otherwise obligated to comply with SCE’s Voltage and VAR schedule that requires the Interconnection Customer to operate its facility in a manner that maintains system voltage within allowable limits, shall be exempt from the Power Factor Adjustment provided that the Interconnection Customer is in compliance with all valid SCE voltage orders. An Interconnection Customer shall mean the entity that interconnects its generating facility with SCE’s transmission system. 13. Voltage Discount: All customers receiving service at 220 kV will have the Distribution rate component of the applicable Delivery Service charges reduced by the corresponding Voltage Discount amount for service metered and delivered at the applicable voltage level, as shown in the RATES section above. In addition, Bundled Service Customers will have the Generation charges reduced by the corresponding Voltage Discount amount for service metered and delivered at the applicable voltage level, as shown in the RATES section. 14. Billing Calculation: A customer’s bill is calculated according to the RATES section and Special Conditions included in this Schedule. The charges listed in the RATES are calculated by multiplying the Total Delivery Service Charges and the Generation Charges, when applicable, by the billing determinants (e.g., kilowatt [kW], kilowatt-hour [kWh], kiloVar [kVAR], etc.). The Total Delivery Service Charges, which include the Customer Charge, CRC, FacilitiesRelated Demand (FRD) Charges, Delivery Energy Charges, and Power Factor Adjustment Charges, are calculated as follows: a. b. c. d. e. Monthly Customer Charge – fixed charge that does not vary based on registered usage or demand; recovers customer service costs, such as service line drop, meter reading, billing, etc. The CRC is determined by multiplying the Standby Demand by the CRC Charges shown in the RATES section. The FRD Charge is determined by multiplying the greater of zero versus the Maximum Demand less the Standby Demand by the Facilities-Related Demand Charges shown in the RATES section. The Delivery Energy Charge is determined by multiplying the total kWh consumption by the Delivery Energy Charges shown in the RATES section. The Power Factor Adjustment is determined by multiplying the billing kVAR demand by the Power Factor Adjustment Charges shown in the RATES section. (Continued) (To be inserted by utility) Advice 3986-E Decision 27D7 Issued by R.O. Nichols Senior Vice President (To be inserted by Cal. PUC) Date Filed Apr 12, 2019 Effective Resolution (N) | | | | | | | (N)
- Page 20 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised TABLE OF CONTENTS Cal. PUC Sheet No. Cal. PUC Sheet No. 66902-E 66856-E Sheet 1 Cal. P.U.C. Sheet No. TITLE PAGE ............................................................................................................................. 11431-E TABLE OF CONTENTS - RATE SCHEDULES ....66902-64842-65130-66857-66858-66903-66860-E ........................................................................................................... 66861-66862-66863-E TABLE OF CONTENTS - LIST OF CONTRACTS AND DEVIATIONS ................................... 66863-E TABLE OF CONTENTS - RULES ................................................................................. 65313-64043-E TABLE OF CONTENTS-INDEX OF COMMUNITIES, MAPS, BOUNDARY DESCRIPTIONS 62213-E TABLE OF CONTENTS - SAMPLE FORMS.. .................. 62213-64447-61576-65710-63318-61631-E ........................................................................................................... 64044-61971-63296-E (T) PRELIMINARY STATEMENT: A. B. C. D. E. F. G. H. I. J. K. L. M. N. O. P. Territory Served ......................................................................................................... 22909-E Description of Service ................................................................................................ 22909-E Procedure to Obtain Service ..................................................................................... 22909-E Establishment of Credit and Deposits ....................................................................... 22909-E General .......................................................................... 45178-45179-45180-53818-45182-E Symbols ..................................................................................................................... 45182-E Gross Revenue Sharing Mechanism .......26584-26585-26586-26587-27195-27196-54092-E .................................................................................................. 51717-53819-27200-27201-E Baseline Service ........................................................... 52027-52028-52029-52030-52031-E Charge Ready Program Balancing Account ................................................... 65510-65511-E Not In Use ............................................................................................................................. -E Nuclear Decommissioning Adjustment Mechanism ........................................ 36582-57779-E Purchase Agreement Administrative Costs Balancing Account ........... 55207-51922-55208-E Income Tax Component of Contributions ....................................................... 58419-58420-E Memorandum Accounts.... 21344-65676-61164-58221-49492-61165-61166-61167-53821-E ........ 50418-42841-61168-64869-64870-44950-44951-44952-44953-42849-42850-42851-E ........ 65677-65678-55623-61171-42856-61172-61173-52033-50419-55048-61174-42863-E ........ 42864-56204-56205-51235-45920-51236-61175-50209-42872-42873-50421-46539-E ........ 42876-42877-42878-42879-42880-42881-42882-54534-53371-56253-44959-42887-E ........ 53321-53322-61176-52551-52552-49928-56235-56236-56237-55144-55145-44029-E ........ 53016-57156-57157-51163-51164-51165-51166-51167-51168-51169-51170-51171-E ................................ 51244-55806-56393-56394-56395-56396-56397-56398-56399-58978E California Alternate Rates for Energy (CARE) Adjustment Clause ................. 34705-41902-E .................................................................................................. 36472-38847-56788-66723-E Not In Use ................................................................................. 27670-27671-27673-27674-E (Continued) (To be inserted by utility) Advice 3986-E Decision 1D3 Issued by R.O. Nichols Senior Vice President (To be inserted by Cal. PUC) Date Filed Apr 12, 2019 Effective Resolution
- Page 21 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised TABLE OF CONTENTS Cal. PUC Sheet No. Cal. PUC Sheet No. 66903-E 66859-E Sheet 6 (Continued) RATE SCHEDULES (Continued) Schedule No. Cal. P.U.C. Title of Sheet Sheet No. GENERAL SERVICE/INDUSTRIAL (Continued) TOU-GS-3 Time-of-Use General Service Demand Metered ............ 66231-66232-66233-66234-E ......... 66772-66773-66774-66775-66239-66240-66241-66242-66891-66892-66245-E .................................................................. 66246-66247-66248-66249-66250-66251-E TOU-GS-3-RTP General Service – Large – Real Time Pricing ..... 66252-66253-66254-66777-66778-E ................................ 66257-66893-66894-66260-66261-66262-66263-66264-66265-E TOU-GS-3-SOP Time-of-Use General Service Super Off Peak Demand Metered ......... 66266-66267-E ............................ 66895-41104-41105-49393-47409-41108-41109-47410-65404-E TOU-8 General Service - Large .... 66268-66269-66270-66271-66272-66273-66274-66275-E .... 66780-66781-66782-66783-66784-66785-66786-66787-66788-66789-66790--E .... 66791-66288-66896-66897-66291-66292-66293-66294-66295-66296-66297--E .............................................................. 66298-66299-66300-66301-66302-66304-E TOU-8-RBU Time-of-Use, General Service, Large, Reliability Back-Up Service ...... 66792-66793-E ..........................................66794-66308-66898-51782-47415-45752-45753-47416-E TOU-8-RTP General Service – Large Real Time Pricing ........ 66309-66310-66311-66312-66795-E .......... 66796-66797-66798-66799-66800-66319-66899-66321-66322-66323-66234-E ............................................66235-66236-66237-66238-66239-66330-66331-66332-E TOU-8-RTP-S General Service – Large Real Time Pricing – Standby... 66333-66334-66335-66336-E ……...66337-66338-66339-66801-66802-66803-66804-66805-66806-66346-66347-E .......... 66348-66349-66350-66351-66352-66353-66354-66900-66356-66357-66358-E ……………………………………….66359-66360-66361-66362-66363-66364-66365-E TOU-8-S Time-Of-Use – General Service – Large – Standby ....... 66366-66367-66368-66807-E 66808-66809-66810-66811-66812-66813-66814-66815-66816-66817-66818-66381-E 66382-66383-66384-66385-66386-66387-66388-66389-66390-66391-66901-66393-E 66394-66394-66395-66396-66397-66398-66399-66400-66401-66402-66403-66404-E ………………………………………………………………………………………… 66405-E AGRICULTURAL/PUMPING AP-I PA-1 PA-2 Agricultural and Pumping - Interruptible 66406-66407-66408-61425-64363-64102-E ............................................................................................. 64103-64104-65846-E Power - Agricultural and Pumping (Connected Load Basis) .. 66409-59202-65819-E ......................... 59204-59205-59206-59208-59209-59210-59211-59212-59213-E Power - Agricultural and Pumping (Demand Basis) .... 66410-65820-59215-59216-E ........................................................... 59217-59218-59219-59220-59221-59222-E (Continued) (To be inserted by utility) Advice 3986-E Decision 6D3 Issued by R.O. Nichols Senior Vice President (To be inserted by Cal. PUC) Date Filed Apr 12, 2019 Effective Resolution (T) (T) (T) (T) (T) (T) (T) (T)
- Page 22 -