Gary A. Stern, Ph.D.
Managing Director, State Regulatory Operations

August 1, 2019
ADVICE 227-G
(U 338-E)
PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
ENERGY DIVISION
Decrease in Santa Catalina Island Gas Cost Adjustment
Billing Factors and the California Alternate Rates for Energy
Surcharge

SUBJECT:

Southern California Edison Company (SCE) hereby submit the following changes to its
gas tariffs applicable to Santa Catalina Island. The revised tariff sheets are listed on
Attachment A and are attached hereto.
PURPOSE
This advice letter revises SCE’s gas tariffs to reflect a decrease in the Santa Catalina
Island Gas Cost Adjustment Billing Factors (GCABFs) and the California Alternate
Rates for Energy (CARE) Surcharge component of base rates for non-CARE gas
customers.
The revised GCABFs are calculated in accordance with the procedures set forth in
Preliminary Statement Part G, Santa Catalina Island Gas Cost Adjustment Clause
(GCAC), of SCE’s gas tariffs as authorized by California Public Utilities Commission
(Commission) Decision (D.)82-04-010.
BACKGROUND
In D.82-04-010, Ordering Paragraph (OP) 2, the Commission authorized SCE to submit
GCAC by advice letters for every 6-month period, with March 1 and September 1 as the
regularly-scheduled revision dates. SCE’s GCABFs and CARE Surcharge were last
revised effective March 1, 2019, as submitted in Advice 223-G, dated January 30,
2019.1
The GCABFs established herein are based on the total GCAC revenue requirement
which reflects: 1) gas expense for the Forecast Period of September 1, 2019, through
1

Advice 223-G was approved by the Commission’s Energy Division on March 26, 2019.

P.O. Box 800

8631 Rush Street

Rosemead, California 91770

(626) 302-9645

Fax (626) 302-6396





- Page 1 -

ADVICE 227-G (U 338-E) -2- August 1, 2019 August 31, 2020 and 2) amortization of the estimated September 1, 2019, balance in the GCAC balancing account over the Forecast Period. Table I (attached) sets forth the calculation of the GCAC balancing account revenue requirement and the fuel revenue requirement. PROPOSED TARIFF CHANGES SCE’s current and revised GCABFs and CARE Surcharge for Santa Catalina Island are listed below: GCABFs Current $/Therm Domestic Baseline Service2 Domestic Non-Baseline Service Other Than Domestic Service CARE Surcharge GCABFs Revised $/Therm 2.36832 2.47955 2.73198 0.06768 2.26320 2.35844 2.60819 0.06543 Preliminary Statement Part G, Section 8 and Schedules G-1 and G-2 are modified to reflect the revised GCABFs. In addition, Schedule G-1-CARE is modified to reflect the revised CARE Surcharge. This advice letter allocates the revenue decrease to Domestic and General Service customers on a System Average Percentage Change (SAPC) basis. This is consistent with the allocation adopted by the Commission in SCE’s previous GCAC advice letters. The decrease in annualized revenues resulting from these changes in rates, based on the therms estimated to be sold during the Forecast Period, is as follows: 2 The GCABF rates, when combined with the base rates, are adjusted to maintain a total NonBaseline to Baseline rate ratio of 1.15:1.
- Page 2 -

ADVICE 227-G (U 338-E) -3- August 1, 2019 Revised Revenue Change From Present Rates Rate Schedule Domestic General Service TOTAL Forecasted Therms Change in Total Revenue ($) % 187,127 295,987 ($19,925) ($37,305) (2.3%) (2.3%) 483,115 ($57,231) (2.3%) OP 5 of D.82-04-010 requires SCE to show the method used to calculate the transportation charges for delivery of propane to Santa Catalina Island. See Tab 5 – Reference 8 of Fact Book. Table II (attached) sets forth the historical quantity and cost of propane to SCE for the 12 months ending June 2019, which includes transportation charges. The average price of propane is also shown by month and for the 12-month period. TIER DESIGNATION Pursuant to General Order (GO) 96-B, Energy Industry Rule 5.1, this advice letter is submitted with a Tier 1 designation. EFFECTIVE DATE This rate change is requested to be effective for service rendered on and after September 1, 2019 pursuant to D.82-04-010. NOTICE Anyone wishing to protest this advice letter may do so by letter via U.S. Mail, facsimile, or electronically, any of which must be received no later than 20 days after the date of this advice letter. Protests should be submitted to:
- Page 3 -

ADVICE 227-G (U 338-E) -4- August 1, 2019 CPUC, Energy Division Attention: Tariff Unit 505 Van Ness Avenue San Francisco, California 94102 E-mail: EDTariffUnit@cpuc.ca.gov Copies should also be mailed to the attention of the Director, Energy Division, Room 4004 (same address above). In addition, protests and all other correspondence regarding this advice letter should also be sent by letter and transmitted via facsimile or electronically to the attention of: Gary A. Stern, Ph.D. Managing Director, State Regulatory Operations Southern California Edison Company 8631 Rush Street Rosemead, California 91770 Telephone (626) 302-9645 Facsimile: (626) 302-6396 E-mail: AdviceTariffManager@sce.com Laura Genao Managing Director, State Regulatory Affairs c/o Karyn Gansecki Southern California Edison Company 601 Van Ness Avenue, Suite 2030 San Francisco, California 94102 Facsimile: (415) 929-5544 E-mail: Karyn.Gansecki@sce.com There are no restrictions on who may submit a protest, but the protest shall set forth specifically the grounds upon which it is based and must be received by the deadline shown above. In accordance with General Rule 4 of GO 96-B, SCE is serving copies of this advice letter to the interested parties shown on the attached Gas GO 96-B service list. Address change requests to the GO 96-B service list should be directed by electronic mail to AdviceTariffManager@sce.com or at (626) 302-3719. For changes to all other service lists, please contact the Commission’s Process Office at (415) 703-2021 or by electronic mail at Process_Office@cpuc.ca.gov. Further, in accordance with Public Utilities Code Section 491, notice to the public is hereby given by submitting and keeping the advice letter at SCE’s corporate headquarters. To view other SCE advice letters submitted with the Commission, log on to SCE’s web site at https://www.sce.com/wps/portal/home/regulatory/advice-letters.
- Page 4 -

ADVICE 227-G (U 338-E) -5- August 1, 2019 For questions, please contact John Montanye at (626) 302-2308 or by electronic mail at John.Montanye@sce.com. Southern California Edison Company /s/ Gary A. Stern Gary A. Stern, Ph.D. GAS:jm:cm Enclosures
- Page 5 -

ADVICE LETTER SUMMARY ENERGY UTILITY MUST BE COMPLETED BY UTILITY (Attach additional pages as needed) Company name/CPUC Utility No.: Southern California Edison Company (U 338-E) Utility type: ELC GAS PLC HEAT ELC = Electric PLC = Pipeline WATER Contact Person: Darrah Morgan Phone #: (626) 302-2086 E-mail: AdviceTariffManager@sce.com E-mail Disposition Notice to: AdviceTariffManager@sce.com EXPLANATION OF UTILITY TYPE GAS = Gas WATER = Water HEAT = Heat (Date Submitted / Received Stamp by CPUC) Tier Designation: 1 Advice Letter (AL) #: 227-G Subject of AL: Decrease in Santa Catalina Island Gas Cost Adjustment Billing Factors and the California Alternate Rates for Energy Surcharge Keywords (choose from CPUC listing): Compliance, Decrease Rates, Balancing Account, Surcharges AL Type: Monthly Quarterly Annual One-Time Other: If AL submitted in compliance with a Commission order, indicate relevant Decision/Resolution #: Decision 82-04-010 Does AL replace a withdrawn or rejected AL? If so, identify the prior AL: Summarize differences between the AL and the prior withdrawn or rejected AL: Confidential treatment requested? Yes No If yes, specification of confidential information: Confidential information will be made available to appropriate parties who execute a nondisclosure agreement. Name and contact information to request nondisclosure agreement/ access to confidential information: Resolution required? Yes No Requested effective date: 9/1/19 No. of tariff sheets: -6- Estimated system annual revenue effect (%): 2.3 Estimated system average rate effect (%): 2.3 When rates are affected by AL, include attachment in AL showing average rate effects on customer classes (residential, small commercial, large C/I, agricultural, lighting). Tariff schedules affected: See Attachment A Service affected and changes proposed1: Pending advice letters that revise the same tariff sheets: None 1 Discuss in AL if more space is needed. Clear Form
- Page 6 -

Protests and all other correspondence regarding this AL are due no later than 20 days after the date of this submittal, unless otherwise authorized by the Commission, and shall be sent to: CPUC, Energy Division Attention: Tariff Unit 505 Van Ness Avenue San Francisco, CA 94102 Email: EDTariffUnit@cpuc.ca.gov Name: Gary A. Stern, Ph.D. Title: Managing Director, State Regulatory Operations Utility Name: Southern California Edison Company Address: 8631 Rush Street City: Rosemead Zip: 91770 State: California Telephone (xxx) xxx-xxxx: (626) 302-9645 Facsimile (xxx) xxx-xxxx: (626) 302-6396 Email: advicetariffmanager@sce.com Name: Laura Genao c/o Karyn Gansecki Title: Managing Director, State Regulatory Affairs Utility Name: Southern California Edison Company Address: 601 Van Ness Avenue, Suite 2030 City: San Francisco State: California Zip: 94102 Telephone (xxx) xxx-xxxx: Facsimile (xxx) xxx-xxxx: (415) 929-5544 Email: karyn.gansecki@sce.com Clear Form
- Page 7 -

ENERGY Advice Letter Keywords Affiliate Direct Access Preliminary Statement Agreements Disconnect Service Procurement Agriculture ECAC / Energy Cost Adjustment Qualifying Facility Avoided Cost EOR / Enhanced Oil Recovery Rebates Balancing Account Energy Charge Refunds Baseline Energy Efficiency Reliability Bilingual Establish Service Re-MAT/Bio-MAT Billings Expand Service Area Revenue Allocation Bioenergy Forms Rule 21 Brokerage Fees Franchise Fee / User Tax Rules CARE G.O. 131-D Section 851 CPUC Reimbursement Fee GRC / General Rate Case Self Generation Capacity Hazardous Waste Service Area Map Cogeneration Increase Rates Service Outage Compliance Interruptible Service Solar Conditions of Service Interutility Transportation Standby Service Connection LIEE / Low-Income Energy Efficiency Storage Conservation LIRA / Low-Income Ratepayer Assistance Street Lights Consolidate Tariffs Late Payment Charge Surcharges Contracts Line Extensions Tariffs Core Memorandum Account Taxes Credit Metered Energy Efficiency Text Changes Curtailable Service Metering Transformer Customer Charge Customer Owned Generation Mobile Home Parks Name Change Transition Cost Transmission Lines Decrease Rates Non-Core Transportation Electrification Demand Charge Non-firm Service Contracts Transportation Rates Demand Side Fund Nuclear Undergrounding Demand Side Management Oil Pipelines Voltage Discount Demand Side Response PBR / Performance Based Ratemaking Wind Power Deposits Portfolio Withdrawal of Service Depreciation Power Lines Clear Form
- Page 8 -

TABLE I SOUTHERN CALIFORNIA EDISON COMPANY CALCULATION OF THE SANTA CATALINA ISLAND GCAC REVENUE REQUIREMENT FOR A SEPTEMBER 1, 2019 REVISION DATE 1/ Line No. Component Amount ($) 1. GAS COST FORECAST 2. Forecast Cost 2/ 3. 4. Plus: 1.05% for Franchise Fees and Uncollectibles Expense Allowance 5. Forecast Gas Revenue Requirement 6. BALANCING ACCOUNT ESTIMATE 7. 8. Forecast Balance in the GCAC Balancing Account as of September 1, 2019 9. 10. Plus: 1.05% for Franchise Fees and Uncollectibles Expense Allowance 11. GCAC Balancing Account Revenue Requirement 12. 13. GCAC Revenue Requirement (line 5 + line 11) 1,076,816 1,088,243 109,650 1,164 110,814 1,199,057 1/ Based on the 12-month Forecast Period beginning September 1, 2019 and a 12-month amortization of the estimated GCAC Balancing Account balance on September 1, 2019. 2/ Based on an estimated usage of: 11,427 598,966 gallons.
- Page 9 -

TABLE II SOUTHERN CALIFORNIA EDISON COMPANY SANTA CATALINA ISLAND GCAC RECORDED MONTHLY PURCHASES OF PROPANE FUEL AND TRANSPORTATION COSTS Line No. Month 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 2018 JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER 2019 JANUARY FEBRUARY MARCH APRIL MAY JUNE 14. 15. Monthly Propane Delivered Purchases Price, FOB of Propane Avalon, Catalina (Gallons) ($/gallon) 1/ (1) (2) Total Cost ($) (3) 75,600 66,450 57,900 53,250 45,900 67,650 1.498 1.553 1.638 1.916 1.853 1.854 113,217 103,170 94,812 102,051 85,049 125,412 56,100 61,950 60,482 45,750 66,150 73,500 2.010 2.154 2.327 1.758 1.494 1.459 112,780 133,440 140,713 80,450 98,839 107,223 TOTAL - 12 Months Ending June 30, 2019 730,682 1.775 1,297,156 1/ Price includes transportation charges. Sales not subject to California Sales Tax.
- Page 10 -

Public Utilities Commission 227-G Cal. P.U.C. Sheet No. Title of Sheet Attachment A Cancelling Cal. P.U.C. Sheet No. Revised 2171-G Preliminary Statements G Revised 2116-G Revised 2172-G Revised 2173-G Schedules G-1 Schedules G-1 Revised 2117-G Revised 2145-G Revised 2174-G Schedules G-1-CARE Revised 2159-G Revised 2175-G Schedules G-2 Revised 2146-G Revised 2176-G Table of Contents Revised 2160-G 1
- Page 11 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised PRELIMINARY STATEMENT G. Cal. PUC Sheet No. Cal. PUC Sheet No. 2171-G 2116-G Sheet 4 (Continued) SANTA CATALINA ISLAND GAS COST ADJUSTMENT CLAUSE (GCAC) (Continued) 8. Gas Cost Adjustment Billing Factors (GCABF) (Continued) Effective Date March 1, 2000 September 1, 2000 March 1, 2001 September 1, 2001 March 1, 2002 September 1, 2002 March 1, 2003 September 1, 2003 March 1, 2004 September 1, 2004 March 1, 2005 September 1, 2005 March 1, 2006 September 1, 2006 March 1, 2007 September 1, 2007 March 1, 2008 September 1, 2008 March 1, 2009 September 1, 2009 March 1, 2010 September 1, 2010 March 1, 2011 September 1, 2011 March 1, 2012 September 1, 2012 March 1, 2013 September 1, 2013 March 1, 2014 September 1, 2014 March 1, 2015 September 1, 2015 March 1, 2016 September 1, 2016 March 1, 2017 September 1, 2017 March 1, 2018 September 1, 2018 March 1, 2019 September 1, 2019 (To be inserted by utility) Advice 227-G Decision 82-04-010 4D3 Applicable to Baseline Service $0.64184 $0.80571 $1.05189 $1.22332 $0.94005 $0.47609 $0.80520 $0.84538 $0.98009 $0.79584 $1.42557 $1.53472 $1.61807 $1.77875 $1.81721 $1.88338 $2.08758 $2.52103 $2.65191 $1.66217 $1.97579 $1.77663 $2.42003 $2.43801 $2.65857 $2.62329 $1.59163 $1.28532 $1.88343 $2.07748 $2.22740 $1.08654 $0.87288 $1.09935 $1.40894 $1.78321 $2.10885 $2.17782 $2.36832 $2.26320 Applicable to Nonbaseline Service $0.47969 $0.66814 $0.95125 $1.14840 $0.82264 $0.28907 $0.66774 $0.71395 $0.86868 $0.65680 $1.38088 $1.50123 $1.59707 $1.78197 $1.82619 $1.90226 $2.13710 $2.63559 $2.78599 $1.64778 $2.01843 $1.78870 $2.54149 $2.57504 $2.82893 $2.78797 $1.59666 $1.24378 $1.92174 $2.14566 $2.31804 $1.00280 $0.75634 $1.01721 $1.37468 $1.80602 $2.18089 $2.26065 $2.47955 $2.35844 Issued by Kevin Payne Chief Executive Officer Applicable to General Service $0.71840 $0.92532 $1.23626 $1.45212 $1.09441 $0.50697 $0.92206 $0.97266 $1.14189 $0.91091 $1.70642 $1.84563 $1.95393 $2.16275 $2.21307 $2.29883 $2.56360 $3.11486 $3.28077 $2.02636 $2.37291 $2.07911 $2.86429 $2.89010 $3.15791 $3.11497 $1.83635 $1.45719 $2.16573 $2.39755 $2.57551 $1.22035 $0.96822 $1.23536 $1.60062 $2.04198 $2.42630 $2.50779 $2.73198 $2.60819 (R) (To be inserted by Cal. PUC) Date Filed Aug 1, 2019 Effective Resolution
- Page 12 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised Schedule G-1 SANTA CATALINA ISLAND DOMESTIC SERVICE Cal. PUC Sheet No. Cal. PUC Sheet No. 2172-G 2117-G Sheet 1 APPLICABILITY Applicable to domestic service of liquefied petroleum gas-air to a single-family accommodation or dwelling. TERRITORY The City of Avalon, and vicinity, Santa Catalina Island. RATES Per Meter Per Day Customer Charge: For 175 cubic feet per hour meter ................................................................... $0.417 For 305 cubic feet per hour meter ................................................................... $0.727 For 400 cubic feet per hour meter ................................................................... $0.953 For 675 cubic feet per hour meter ................................................................... $1.609 For 1,000 cubic feet per hour meter ..................................................................$2.383 For 2,000 cubic feet per hour meter ..................................................................$4.751 For 3,000 cubic feet per hour meter ..................................................................$7.124 For 4,000 cubic feet per hour meter ..................................................................$9.499 For 5,000 cubic feet per hour meter ................................................................ $11.876 Energy Charge (To be added to Customer Charge): Baseline Service, per therm ............................................................................... $3.57954 Nonbaseline Service, per therm ........................................................................ $4.11647 (R) (R) The rates above include Base Rates and the applicable Adjustment Rates as shown below: (Continued) (To be inserted by utility) Advice 227-G Decision 82-04-010 1D3 Issued by Kevin Payne Chief Executive Officer (To be inserted by Cal. PUC) Date Filed Aug 1, 2019 Effective Resolution
- Page 13 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised Cal. PUC Sheet No. Cal. PUC Sheet No. Schedule G-1 SANTA CATALINA ISLAND DOMESTIC SERVICE (Continued) 2173-G 2145-G Sheet 2 ENERGY CHARGE COMPONENTS Base Rates*: Baseline Service, per therm ................................................................................ $1.31387 Nonbaseline Service, per therm ......................................................................... $1.75556 * Base Rates include CARE Surcharge of $0.06543 per therm, for both Baseline and Nonbaseline Service. (R) (R) (R) Adjustment Rates: Gas Cost Adjustment Billing Factor: Baseline Service, per therm ...................................................................... $2.26320 Nonbaseline Service, per therm ................................................................ $2.35844 (R) (R) PUC Reimbursement Fee, per therm ................................................................. $0.00247 The Gas Cost Adjustment Rate is described in Part G of the Preliminary Statement. The PUC Reimbursement Fee is described in Schedule RF-G. SPECIAL CONDITIONS 1. Minimum Customer Charge: Service to customers shall be on an annual basis only with an annual Minimum Customer Charge of 365 times the applicable daily Customer Charge rate payable monthly, or as billed by the Company. 2. Seasonal Service: For summer cottage customers and others who normally require service for only part of the year, this schedule is applicable only on an annual contract. 3. Baseline Service: The rates above are subject to Baseline Service provisions which are described in Part F of the Preliminary Statement. The applicable baseline quantity of gas to be billed under rates designated as Applicable to Baseline Service shall be the total of any Medical Baseline Allocation permitted under Part F, Paragraph 4 of the Preliminary Statement, plus the applicable daily baseline allocation shown below by Season and Time Period. Season Winter Summer (To be inserted by utility) Advice 227-G Decision 82-04-010 2D5 Time Period November 1 through April 30 May 1 through October 31 Issued by Kevin Payne Chief Executive Officer Therms Per Meter Day 1.348 0.526 (To be inserted by Cal. PUC) Date Filed Aug 1, 2019 Effective Resolution
- Page 14 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised Cal. PUC Sheet No. Cal. PUC Sheet No. 2174-G 2159-G Schedule G-1-CARE Sheet 1 SANTA CATALINA ISLAND CALIFORNIA ALTERNATE RATES FOR ENERGY (CARE) DOMESTIC SERVICE APPLICABILITY Applicable to domestic service to CARE households residing in a permanent single-family accommodation where a customer meets all the Special Conditions of this Schedule. Customers who receive gas service under Schedule G-1 are eligible for this Schedule. TERRITORY The City of Avalon, Santa Catalina Island. RATES The bill as determined under Schedule G-1 which would otherwise be applicable, minus the CARE surcharge, less a 20% discount excluding the PUCRF. SPECIAL CONDITIONS 1. CARE Customers are exempt from a CARE Surcharge of $0.06543/Therm for Baseline and Non-Baseline Service. The 20% discount applies to the Customer Charge and GCAC and base rate (excluding the CARE surcharge portion) charges only. The total Schedule G-1-CARE bill is thus equal to the Schedule G-1 bill, minus CARE surcharge, minus the 20% discount. 2. (R) CARE Household: A CARE Household is a household where the total gross income from all sources is less than shown on the table below based on the number of persons in the household. Total gross income shall include income from all sources, both taxable and nontaxable. Persons who are claimed as a dependent on another person’s income tax return are not eligible. These income limits are effective as of June 1, 2019. No. of Persons In Household 1-2 3 4 5 6 7 8 Total Gross Annual Income 33,820 42,660 51,500 60,340 69,180 78,020 86,840 For each additional person residing in the household, add $8,840 annually. (Continued) (To be inserted by utility) Advice 227-G Decision 82-04-010 1D3 Issued by Kevin Payne Chief Executive Officer (To be inserted by Cal. PUC) Date Filed Aug 1, 2019 Effective Resolution
- Page 15 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised Schedule G-2 SANTA CATALINA ISLAND GENERAL SERVICE Cal. PUC Sheet No. Cal. PUC Sheet No. 2175-G 2146-G Sheet 1 APPLICABILITY Applicable to general service of liquefied petroleum gas-air. TERRITORY The City of Avalon, and vicinity, Santa Catalina Island. RATES Per Meter Per Day Customer Charge: For 175 cubic feet per hour meter ................................................................... $0.417 For 305 cubic feet per hour meter ................................................................... $0.727 For 400 cubic feet per hour meter ................................................................... $0.953 For 675 cubic feet per hour meter ................................................................... $1.609 For 1,000 cubic feet per hour meter ..................................................................$2.383 For 2,000 cubic feet per hour meter ..................................................................$4.751 For 3,000 cubic feet per hour meter ..................................................................$7.124 For 4,000 cubic feet per hour meter ..................................................................$9.499 For 5,000 cubic feet per hour meter ................................................................ $11.876 Energy Charge (To be added to Customer Charge): All therms, per therm ..................................... ................................................... $5.27475 (R) The rates above include Base Rates and the applicable Adjustment Rates as shown below: ENERGY CHARGE COMPONENTS Base Rates*: All Therms, per therm ........................................................................................ $2.66409 * (R) (R) Base Rate includes CARE Surcharge of $0.06543 per Therm. Adjustment Rates: Gas Cost Adjustment Billing Factor, per therm ................................................. $2.60819 (R) PUC Reimbursement Fee, per therm ................................................................ $0.00247 The Gas Cost Adjustment Rate is described in Part G of the Preliminary Statement. The PUC Reimbursement Fee is described in Schedule RF-G. (Continued) (To be inserted by utility) Advice 227-G Decision 82-04-010 1D4 Issued by Kevin Payne Chief Executive Officer (To be inserted by Cal. PUC) Date Filed Aug 1, 2019 Effective Resolution
- Page 16 -

Southern California Edison Rosemead, California (U 338-E) Cancelling Revised Revised TABLE OF CONTENTS Cal. PUC Sheet No. Cal. PUC Sheet No. 2176-G 2160-G Sheet 1 Cal. P.U.C. Sheet No. TITLE PAGE .................................................................................................................................. 2104-G TABLE OF CONTENTS - RATE SCHEDULES ........................................................................... 2176-G TABLE OF CONTENTS - LIST OF CONTRACTS AND DEVIATIONS ...................................... 1980-G TABLE OF CONTENTS - RULES ................................................................................................. 2105-G TABLE OF CONTENTS - SAMPLE FORMS ............................................................................... 1981-G (T) PRELIMINARY STATEMENT: A. B. C. D. E. F. G. H. Territory Served by the Utility ............................................................................................... 1388-G Types and Classes of Service ............................................................................................. 1388-G Procedure to Obtain Service ................................................................................................ 1388-G Interest ................................................................................................................................... 1388-G Symbols ................................................................................................................................ 1388-G Baseline Service .......................................................................................................... 1389-1826-G Santa Catalina Island Gas Cost Adjustment Clause (GCAC) ................. 1391-1392-1393-2171-G Income Tax Component of Contributions Provision ................................................... 2047-1892-G (T) SERVICE AREA MAP ......................................................................................................................... 3-G RATE SCHEDULES Schedule No. DE G-1 G-1-CARE G-2 G-OBR GM G-SE RF-G Title of Sheet Cal. P.U.C. No. Domestic Service to Utility Employees .................................................................. 1398-G Domestic Service ........................................................................................... 2172-2173-G Domestic Service ........................................................................................... 2174-1132-G General Service .............................................................................................2175-1401-G Santa Catalina Island On-Bill Repayment Pilot Program….. 2020-1633-1634-1635-G ............................................... ………………………………1636-1637-1638-1813-1814-G Domestic Service, Multifamily Accommodation ..................................................... 1402-G Service Establishment Charge ............................................................................... 1403-G Surcharge to Fund Public Utilities Commission Reimbursement Fee.................. 2035-G (T) (T) (T) LIST OF CONTRACTS AND DEVIATIONS Cal. P.U.C. Sheet No. List of Contracts and Deviations ...................................................................................................... 696-G (Continued) (To be inserted by utility) Advice 227-G Decision 82-04-010 1D3 Issued by Kevin Payne Chief Executive Officer (To be inserted by Cal. PUC) Date Filed Aug 1, 2019 Effective Resolution