August 2, 2019

Advice 5573-E-A
(Pacific Gas and Electric Company ID U 39 E)

Public Utilities Commission of the State of California
Subject:

Supplemental: July 1, 2019 Electric Rate Change

Purpose
Pacific Gas and Electric Company (PG&E) submits this Tier 1 supplemental advice
letter to revise certain electric rates and tariffs effective July 1, 2019, based on
inadvertent errors discovered since submittal. Tariff sheets affected by this rate change
are provided in Attachment 1.
Background
Advice 5573-E submitted electric rate changes required by (1) D.19-02-023 approving
PG&E’s 2019 ERRA Forecast Application (A.18-06-001), with modifications, including
the change to 2019 forecast sales; (2) D. 18-08-013 implementing specific rate design
changes for Option R of Schedules E-19 and E-20; and (3) reformatting of Electric Rate
Schedule E-ERA – Energy Rate Adjustment resulting in a consolidation of the tariff from
four pages down to a single page.
Since submittal of Advice 5573-E, two errors have been identified in the design of the
rates for Option R of Schedules E-19 and E-20. Those errors are described in detail
below.
The first error was found in the Public Purpose Program (PPP) rate for Schedule E-20T,
Option R. The PPP rate for Option R should be equal to the PPP rate non-Option R
service under Schedule E-20T. Due to a programing error, the Option R PPP rate was
approximately twice the appropriate value leading also to an error in the total energy
rates for Schedule E-20T, Option R.
Second, the generation rates for all Option R rates of Schedule E-19 and E-20 were
found to be in error. This error was caused by inadvertently imputing additional revenue
in the process of designing the rates. As a result, the generation energy rates and total
energy rates were too high.





- Page 1 -

Advice 5573-E-A -2- August 2, 2019 These errors, and the correction of them, do not impact the rates on any other rate schedules. Tariff Revisions The corrected versions of Schedule E-19 and Schedule E-20, for Option R are provided as Attachment 1. PG&E will begin the process of correcting rates going forward, as well as correcting past bills, upon submittal of this advice letter. PG&E notes that the first error described above affecting the PPP rate for Option R of Schedule E-20T was first submitted for rates effective May 1, 2019. PG&E will correct bills for this error for this limited group of customers effective May 1, 2019. Protests Pursuant to CPUC General Order 96-B, Section 7.5.1, PG&E hereby requests the protest period be waived. Effective Date PG&E requests that this Tier 1 advice letter become effective on July 1, 2019. Notice In accordance with General Order 96-B, Section IV, a copy of this advice letter is being sent electronically and via U.S. mail to parties shown on the attached list and the parties on the service list for A.16-06-013 and A.18-06-001. Address changes to the General Order 96-B service list should be directed to PG&E at email address PGETariffs@pge.com. For changes to any other service list, please contact the Commission’s Process Office at (415) 703-2021 or at Process_Office@cpuc.ca.gov. Send all electronic approvals to PGETariffs@pge.com. Advice letter submittals can also be accessed electronically at: http://www.pge.com/tariffs/. /S/ Erik Jacobson Director, Regulatory Relations Attachments cc: Service List A. 16-06-013, A.18-06-001
- Page 2 -

ADVICE LETTER SUMMARY ENERGY UTILITY MUST BE COMPLETED BY UTILITY (Attach additional pages as needed) Company name/CPUC Utility No.: Pacific Gas and Electric Company (ID U39E) Utility type: ELC GAS PLC ✔ HEAT ELC = Electric PLC = Pipeline WATER Contact Person: Yvonne Yang Phone #: (415)973-2094 E-mail: PGETariffs@pge.com E-mail Disposition Notice to: Yvonne.Yang@pge.com EXPLANATION OF UTILITY TYPE GAS = Gas WATER = Water HEAT = Heat (Date Submitted / Received Stamp by CPUC) Tier Designation: 1 Advice Letter (AL) #: 5573-E-A Subject of AL: Supplemental: July 1, 2019 Electric Rate Change Keywords (choose from CPUC listing): Compliance AL Type: Monthly Quarterly Annual ✔ One-Time Other: If AL submitted in compliance with a Commission order, indicate relevant Decision/Resolution #: D.19-02-023 and D.18-08-013 Does AL replace a withdrawn or rejected AL? If so, identify the prior AL: No Summarize differences between the AL and the prior withdrawn or rejected AL: Yes Yes ✔ No ✔ No No. of tariff sheets: 6 7/1/19 Estimated system annual revenue effect (%): N/A Estimated system average rate effect (%): N/A When rates are affected by AL, include attachment in AL showing average rate effects on customer classes (residential, small commercial, large C/I, agricultural, lighting). Tariff schedules affected: See attachment 1 Service affected and changes proposed1: N/A Pending advice letters that revise the same tariff sheets: 1 Discuss in AL if more space is needed. N/A Clear Form
- Page 3 -

Protests and all other correspondence regarding this AL are due no later than 20 days after the date of this submittal, unless otherwise authorized by the Commission, and shall be sent to: CPUC, Energy Division Attention: Tariff Unit 505 Van Ness Avenue San Francisco, CA 94102 Email: EDTariffUnit@cpuc.ca.gov Name: Erik Jacobson, c/o Megan Lawson Title: Director, Regulatory Relations Utility Name: Pacific Gas and Electric Company Address: 77 Beale Street, Mail Code B13U City: San Francisco, CA 94177 Zip: 94177 State: California Telephone (xxx) xxx-xxxx: (415)973-2093 Facsimile (xxx) xxx-xxxx: (415)973-3582 Email: PGETariffs@pge.com Name: Title: Utility Name: Address: City: State: District of Columbia Telephone (xxx) xxx-xxxx: Facsimile (xxx) xxx-xxxx: Email: Zip: Clear Form
- Page 4 -

Attachment 1 Advice 5573-E-A Cal P.U.C. Sheet No. Title of Sheet Cancelling Cal P.U.C. Sheet No. 44752-E ELECTRIC SCHEDULE E-19 MEDIUM GENERAL DEMAND-METERED TOU SERVICE Sheet 7 44089-E 44753-E ELECTRIC SCHEDULE E-19 MEDIUM GENERAL DEMAND-METERED TOU SERVICE Sheet 9 44091-E 44754-E ELECTRIC SCHEDULE E-20 SERVICE TO CUSTOMERS WITH MAXIMUM DEMANDS of 1000 KILOWATTS or MORE Sheet 5 44094-E 44755-E ELECTRIC SCHEDULE E-20 SERVICE TO CUSTOMERS WITH MAXIMUM DEMANDS of 1000 KILOWATTS or MORE Sheet 6 44095-E 44756-E ELECTRIC TABLE OF CONTENTS Sheet 1 44723-E 44757-E ELECTRIC TABLE OF CONTENTS Sheet 4 44682-E Page 1 of 1
- Page 5 -

Cancelling U 39 Revised Revised Cal. P.U.C. Sheet No. Cal. P.U.C. Sheet No. San Francisco, California ELECTRIC SCHEDULE E-19 MEDIUM GENERAL DEMAND-METERED TOU SERVICE 3. 44752-E 44089-E Sheet 7 Rates: (Cont’d.) TOTAL RATES FOR OPTION R (for qualifying solar customers as set forth in Section 20) Total Customer/Meter Charge Rates Customer Charge Mandatory E-19 ($ per meter per day) Secondary Voltage Primary Voltage Transmission Voltage $19.71253 $32.85421 $59.13758 Customer Charge with SmartMeter™ ($ per meter per day) $4.59959 $4.59959 $4.59959 Customer Charge without SmartMeterTM Customer Charge Rate V ($ per meter per day) Customer Charge Rate W ($ per meter per day) Customer Charge Rate X ($ per meter per day) $4.77700 $4.63507 $4.77700 $4.77700 $4.63507 $4.77700 $4.77700 $4.63507 $4.77700 Customer Charge Voluntary E-19: Total Demand Rates ($ per kW) Maximum Peak Demand Summer Maximum Part-Peak Demand Summer Maximum Demand Summer Maximum Part-Peak Demand Winter Maximum Demand Winter $1.59 $0.55 $19.10 $0.03 $19.10 (R) (R) (R) (R) (R) (R) (R) $1.43 $0.48 $15.87 $0.04 $15.87 Total Energy Rates ($ per kWh) Peak Summer Part-Peak Summer Off-Peak Summer Part-Peak Winter Off-Peak Winter $0.38490 $0.18032 $0.09577 $0.12049 $0.10333 (I) (I) (I) (I) (I) $0.37059 $0.16960 $0.08926 $0.11204 $0.09616 (I) (I) (I) (I) (I) Power Factor Adjustment Rate ($/kWh/%) $0.00005 (R) $0.00005 $0.00 $0.00 $10.39 (R) $0.00 $10.39 (R) $0.30694 $0.15084 $0.08818 $0.10928 $0.09480 (I) (I) (I) (I) (I) $0.00005 Total bundled service charges shown on customers’ bills are unbundled according to the component rates shown below. PDP charges and credits are all generation and are not included below. (Continued) Advice Decision 5573-E-A D.19-02-023 & D.18-08-013 Issued by Robert S. Kenney Vice President, Regulatory Affairs Submitted Effective Resolution August 2, 2019 July 1, 2019
- Page 6 -

Cancelling U 39 Revised Revised Cal. P.U.C. Sheet No. Cal. P.U.C. Sheet No. San Francisco, California ELECTRIC SCHEDULE E-19 MEDIUM GENERAL DEMAND-METERED TOU SERVICE 3. 44753-E 44091-E Sheet 9 Rates: (Cont’d.) UNBUNDLING OF TOTAL RATES FOR OPTION R (Cont’d.) (for qualifying solar customers as set forth in Section 20) Customer/Meter Charge Rates: Customer and meter charge rates provided in the Total Rates section above are assigned entirely to the unbundled distribution component. Secondary Voltage Primary Voltage Transmission Voltage Energy Charges by Components ($ per kWh) Generation: Peak Summer Part-Peak Summer Off-Peak Summer Part-Peak Winter Off-Peak Winter $0.30801 $0.14017 $0.07276 $0.09693 $0.08032 (I) (I) (I) (I) (I) $0.29343 $0.13022 $0.06671 $0.08876 $0.07361 (I) (I) (I) (I) (I) $0.28523 $0.12913 $0.06647 $0.08757 $0.07309 Distribution**: Peak Summer Part-Peak Summer Off-Peak Summer Part-Peak Winter Off-Peak Winter $0.05448 $0.01774 $0.00060 $0.00115 $0.00060 (I) (I) (I) (I) (I) $0.05545 $0.01767 $0.00084 $0.00157 $0.00084 (I) (I) (I) (I) (I) $0.00000 $0.00000 $0.00000 $0.00000 $0.00000 Transmission Rate Adjustments* (all usage) Public Purpose Programs (all usage) Nuclear Decommissioning (all usage) Competition Transition Charge (all usage) Energy Cost Recovery Amount (all usage) DWR Bond (all usage) New System Generation Charge (all usage)** California Climate Credit (all usage – E-19V only)*** $0.00327 $0.01129 $0.00088 $0.00104 (I) ($0.00057) $0.00503 $0.00147 (R) $0.00000 $0.00327 $0.01059 (R) $0.00088 $0.00104 (I) ($0.00057) $0.00503 $0.00147 (R) $0.00000 (I) (I) (I) (I) (I) $0.00327 $0.01059 (R) $0.00088 $0.00104 (I) ($0.00057) $0.00503 $0.00147 (R) $0.00000 _________________________ * Transmission, Transmission Rate Adjustments, and Reliability Service charges are combined for presentation on customer bills. ** Distribution and New System Generation Charges are combined for presentation on customer bills. *** Only customers that qualify as Small Businesses – California Climate Credit under Rule 1 are eligible for the California Climate Credit. (Continued) Advice Decision 5573-E-A D.19-02-023 & D.18-08-013 Issued by Robert S. Kenney Vice President, Regulatory Affairs Submitted Effective Resolution August 2, 2019 July 1, 2019
- Page 7 -

Cancelling U 39 Revised Revised Cal. P.U.C. Sheet No. Cal. P.U.C. Sheet No. San Francisco, California ELECTRIC SCHEDULE E-20 SERVICE TO CUSTOMERS WITH MAXIMUM DEMANDS of 1000 KILOWATTS or MORE 3. 44754-E 44094-E Sheet 5 RATES: (Cont’d.) TOTAL RATES FOR OPTION R (for qualifying solar customers as set forth in Section 18) Secondary Voltage $39.42505 Total Customer/Meter Charge Rates Customer Charge Mandatory E-20 ($ per meter per day) Total Demand Rates ($ per kW) Maximum Peak Demand Summer Maximum Part-Peak Demand Summer Maximum Demand Summer Maximum Part-Peak Demand Winter Maximum Demand Winter Primary Voltage $49.28131 $1.52 $0.52 $19.24 $0.01 $19.24 (R) (R) (R) Total Energy Rates ($ per kWh) Peak Summer Part-Peak Summer Off-Peak Summer Part-Peak Winter Off-Peak Winter $0.35156 $0.16914 $0.09015 $0.11305 $0.09725 Power Factor Adjustment Rate ($/kWh/%) $0.00005 Transmission Voltage $65.70842 (R) (R) (R) (R) $1.55 $0.52 $16.91 $0.03 $16.91 (I) (I) (I) (I) (I) $0.36806 $0.16554 $0.08771 $0.11052 $0.09468 (I) (I) (I) (I) (I) (R) $0.00005 $0.00 $0.00 $9.68 (R) $0.00 $9.68 (R) $0.30948 $0.14085 $0.08078 $0.10149 $0.08727 (R) (R) (R) (R) (R) $0.00005 Total bundled service charges shown on customers’ bills are unbundled according to the component rates shown below. PDP charges and credits are all generation and are not included below. (Continued) Advice Decision 5573-E-A D.19-02-023 & D.18-08-013 Issued by Robert S. Kenney Vice President, Regulatory Affairs Submitted Effective Resolution August 2, 2019 July 1, 2019
- Page 8 -

Cancelling U 39 Revised Revised Cal. P.U.C. Sheet No. Cal. P.U.C. Sheet No. San Francisco, California ELECTRIC SCHEDULE E-20 SERVICE TO CUSTOMERS WITH MAXIMUM DEMANDS of 1000 KILOWATTS or MORE 3. 44755-E 44095-E Sheet 6 Rates: (Cont’d.) UNBUNDLING OF TOTAL RATES FOR OPTION R (for qualifying solar customers as set forth in Section 18) Customer/Meter Charge Rates: Customer and meter charge rates provided in the Total Rates section above are assigned entirely to the unbundled distribution component. Demand Rates by Components ($ per kW) Generation: Maximum Peak Demand Summer Maximum Part-Peak Demand Summer Maximum Demand Summer Maximum Part-Peak Demand Winter Maximum Demand Winter Distribution**: Maximum Peak Demand Summer Maximum Part-Peak Demand Summer Maximum Demand Summer Maximum Part-Peak Demand Winter Maximum Demand Winter Secondary Voltage Primary Voltage $0.00 $0.00 $0.00 $0.00 $0.00 $1.52 $0.52 $10.38 $0.01 $10.38 Transmission Voltage $0.00 $0.00 $0.00 $0.00 $0.00 (R) (R) (R) (R) $1.55 $0.52 $8.05 $0.03 $8.05 $0.00 $0.00 $0.00 $0.00 $0.00 (R) (R) (R) (R) Transmission Maximum Demand* Reliability Services Maximum Demand* $8.61 $0.25 Energy Rates by Component ($ per kWh) Generation: Peak Summer Part-Peak Summer Off-Peak Summer Part-Peak Winter Off-Peak Winter $0.28102 $0.13109 $0.06788 $0.09056 $0.07498 (I) (I) (I) (I) (I) $0.29766 $0.12910 $0.06623 $0.08851 $0.07320 (I) (I) (I) (I) (I) $0.28962 $0.12099 $0.06092 $0.08163 $0.06741 Distribution**: Peak Summer Part-Peak Summer Off-Peak Summer Part-Peak Winter Off-Peak Winter $0.04862 $0.01613 $0.00035 $0.00057 $0.00035 (I) (I) (I) (I) (I) $0.04928 $0.01532 $0.00036 $0.00089 $0.00036 (I) (I) (I) (I) (I) $0.00329 $0.01033 $0.00088 $0.00094 (I) ($0.00057) $0.00503 $0.00122 (R) $0.00329 $0.00913 $0.00088 $0.00088 ($0.00057) $0.00503 $0.00122 (R) (R) $0.00000 $0.00000 $0.00000 $0.00000 $0.00000 Transmission Rate Adjustments* (all usage) Public Purpose Programs (all usage) Nuclear Decommissioning (all usage) Competition Transition Charge (all usage) Energy Cost Recovery Amount (all usage) DWR Bond (all usage) New System Generation Charge (all usage)** $8.61 $0.25 $0.00 $0.00 $0.82 $0.00 $0.82 $0.00329 $0.01107 (R) $0.00088 $0.00100 (I) ($0.00057) $0.00503 $0.00122 (R) $8.61 $0.25 (I) (I) (I) (I) (I) (R) (I) (R) * Transmission, Transmission Rate Adjustments, and Reliability Service charges are combined for presentation on customer bills. ** Distribution and New System Generation Charges are combined for presentation on customer bills. (Continued) Advice Decision 5573-E-A D.19-02-023 & D.18-08-013 Issued by Robert S. Kenney Vice President, Regulatory Affairs Submitted Effective Resolution August 2, 2019 July 1, 2019
- Page 9 -

Cancelling U 39 Revised Revised Cal. P.U.C. Sheet No. Cal. P.U.C. Sheet No. 44756-E 44723-E San Francisco, California ELECTRIC TABLE OF CONTENTS Sheet 1 TABLE OF CONTENTS SCHEDULE CAL P.U.C. SHEET NO. TITLE OF SHEET Title Page ............................................................................................................................... 44756-E Rate Schedules ......................................... 44680,44681,44757,44683,44684,44685,43935,44177-E Preliminary Statements ........................... 44686,44687,42856*,43670,41723,40591,44724,44725-E Rules ................................................................................................................ 43022,43023,43210-E Maps, Contracts and Deviations ............................................................................................ 37960-E Sample Forms ... 40925*,37631,41151*,41573*, 37632,41152*,41153,37769,44035,40671,37169-E (T) (T) (Continued) Advice Decision 5573-E-A D.19-02-023 & D.18-08-013 Issued by Robert S. Kenney Vice President, Regulatory Affairs Submitted Effective Resolution August 2, 2019 July 1, 2019
- Page 10 -

Cancelling U 39 Revised Revised Cal. P.U.C. Sheet No. Cal. P.U.C. Sheet No. 44757-E 44682-E San Francisco, California ELECTRIC TABLE OF CONTENTS TITLE OF SHEET SCHEDULE Sheet 4 CAL P.U.C. SHEET NO. Rate Schedules Commercial/Industrial A-1 A-6 A-10 A-15 E-19 E-20 E-31 E-CARE E-CSAC E-PWF E-REMAT E-SRG EDR EITE Small General Service ............................................................. 43286,41408,44057,44058,44059, ......................................................................... 31249,40834,43721,31252,43153,31254,44486-E Small General Time-of-Use Service ........................................ 36652,43290,44066,44067,25981*, ...............................................................................................43732,35784,43159,43160,44488-E Medium General Demand-Metered Service ........................... 35410,43287,44060,44061,44062, ...................................... 44063,29081,29082,40836,43726,29085,29086,43156,43157,44487-E Direct-Current General Service ........................................................ 44064,44065,31442,43729-E Medium General Demand-Metered Time-of-Use Service ....... 29090,43295,43296,44086,44087, ....................................... 44088,44089,44090,47091,35054,35055,37144,35057,35058,35059, (T) ............................................... 43764,35392,35062,43169,40726,44491,42860,43675,43676-E Service to Customers with Maximum Demands of 1,000 Kilowatts or More ............ 43299,42861, .............................................................44092,44093,44754,44755,35069,35070,37145,35072, (T) .......................................................... 43769,35393,43171,40730,44492,42863,43677,43678-E Distribution Bypass Deferral Rate ...............................................................20620,24899,20622-E CARE Program Service for Qualified Nonprofit Group-Living and Qualified Agricultural Employee Housing Facilities ............................................................................................ 44098-E Commercial Smart A/C Program ................................................................32823,43927,43928-E Section 399.20 PPA ...................................................................................32735, 30264,30759-E Renewable Market Adjusting Tariff (ReMAT) .......................... 32736,32737,32738,32739,32740, ..................................................................... 32741,32742,32743,32744,32745,32746,32747-E Small Renewable Generator PPA ...............................................................32748,30266,30760-E Economic Development Rate .......................... 43025,43026,43027,43028,43029,43030,43031-E Emissions-Intensive and Trade-Exposed Customer Greenhouse Gas Allowance Revenue Provisions ....................................................................................35091,35092,35093-E (Continued) Advice Decision 5573-E-A D.19-02-023 & D.18-08-013 Issued by Robert S. Kenney Vice President, Regulatory Affairs Submitted Effective Resolution August 2, 2019 July 1, 2019
- Page 11 -

PG&E Gas and Electric Advice Submittal List General Order 96-B, Section IV AT&T Albion Power Company Alcantar & Kahl LLP Alta Power Group, LLC Anderson & Poole Atlas ReFuel BART Barkovich & Yap, Inc. P.C. CalCom Solar California Cotton Ginners & Growers Assn California Energy Commission California Public Utilities Commission California State Association of Counties Calpine Cameron-Daniel, P.C. Casner, Steve Cenergy Power Center for Biological Diversity City of Palo Alto City of San Jose Clean Power Research Coast Economic Consulting Commercial Energy County of Tehama - Department of Public Works Crossborder Energy Crown Road Energy, LLC Davis Wright Tremaine LLP Day Carter Murphy Dept of General Services Don Pickett & Associates, Inc. Douglass & Liddell Downey & Brand East Bay Community Energy Ellison Schneider & Harris LLP Energy Management Service Engineers and Scientists of California Evaluation + Strategy for Social Innovation GenOn Energy, Inc. Goodin, MacBride, Squeri, Schlotz & Ritchie Green Charge Networks Green Power Institute Hanna & Morton ICF International Power Technology Intestate Gas Services, Inc. Kelly Group Ken Bohn Consulting Keyes & Fox LLP Leviton Manufacturing Co., Inc. Linde Los Angeles County Integrated Waste Management Task Force Los Angeles Dept of Water & Power MRW & Associates Manatt Phelps Phillips Marin Energy Authority McKenzie & Associates Modesto Irrigation District Morgan Stanley NLine Energy, Inc. NRG Solar Office of Ratepayer Advocates OnGrid Solar Pacific Gas and Electric Company Peninsula Clean Energy Pioneer Community Energy Praxair Redwood Coast Energy Authority Regulatory & Cogeneration Service, Inc. SCD Energy Solutions SCE SDG&E and SoCalGas SPURR San Francisco Water Power and Sewer Seattle City Light Sempra Utilities Southern California Edison Company Southern California Gas Company Spark Energy Sun Light & Power Sunshine Design Tecogen, Inc. TerraVerde Renewable Partners Tiger Natural Gas, Inc. TransCanada Troutman Sanders LLP Utility Cost Management Utility Power Solutions Utility Specialists Verizon Water and Energy Consulting Wellhead Electric Company Western Manufactured Housing Communities Association (WMA) Yep Energy